3918 1/4-1/2 W 28TH ST 90018
Certificate Information: 3918 1/4-1/2 W 28TH ST 90018
- Application / Permit
- 25010-10000-02010
- Plan Check / Job No.
- B25LA18706
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story detached ADU duplex per GC 66323(a)(4)
- Permit Issued
- Issued on 8/25/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2025 | MATTHEW TORRES |
| Corrections Issued | 5/17/2025 | MATTHEW TORRES |
| Quality Review Completed | 5/22/2025 | KEN GILL |
| Building Plans Picked Up | 5/30/2025 | APPLICANT |
| Applicant returned to address corrections | 8/14/2025 | MATTHEW TORRES |
| Plan Check Approved | 8/21/2025 | MATTHEW TORRES |
| Issued | 8/25/2025 | APPLICANT |
| CofO in Progress | 5/4/2026 | JUSTIN HAWLEY |
| Permit Finaled | 5/5/2026 | DEROLD HAUFF |
| CofO Issued | 5/5/2026 | DEROLD HAUFF |
| Permit Finaled | 5/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2025 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 5/25/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 6/5/2025 | ABEL CASILLAS |
| Construction near power lines | Cleared | 8/20/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/16/2025 | Partial Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 9/19/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Corrections Issued | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 11/7/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Rough | 11/7/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Rough | 11/7/2025 | Corrections Issued | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 11/13/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 11/13/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/13/2025 | Partial Approval | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 11/13/2025 | Approved | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 11/13/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 11/19/2025 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 12/3/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 12/3/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/3/2025 | Approved | JUSTIN HAWLEY |
| Shower Pan | 12/3/2025 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 1/6/2026 | Corrections Issued | JUSTIN HAWLEY |
| Underground Mechanical | 1/6/2026 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 1/22/2026 | Corrections Issued | ALEX COLIN |
| Underground Mechanical | 1/26/2026 | Partial Approval | ENRIQUE MIRELES |
| Final | 2/17/2026 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 2/17/2026 | Approved | JUSTIN HAWLEY |
| Green Building Final | 2/17/2026 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Not Required | JUSTIN HAWLEY |
| Smoke Detectors | 2/17/2026 | Approved | JUSTIN HAWLEY |
| Final | 3/10/2026 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Final | 4/6/2026 | Approved | WILLIAM SIERRA |
| Final | 4/6/2026 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 4/6/2026 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 4/6/2026 | Approved | WILLIAM SIERRA |
| Service/Power Release | 4/6/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 4/7/2026 | Corrections Issued | JUSTIN HAWLEY |
| Final | 5/4/2026 | OK to Issue CofO | JUSTIN HAWLEY |
| Service/Power Release | 5/4/2026 | Approved | JUSTIN HAWLEY |