232 1/2 S WINDSOR BLVD 90004
Certificate Information: 232 1/2 S WINDSOR BLVD 90004
- Application / Permit
- 25010-10000-01988
- Plan Check / Job No.
- B25LA18444
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. PROPOSED 2-STORY DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE. GROUND FLOOR WILL CONTAIN RECREATION ROOM AND GARAGE AND SECOND FLOOR WILL BE ADU.
- Permit Issued
- Issued on 10/9/2025
- Issuing Office
- Current Status
- Issued on 10/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2025 | MICHAEL LOPEZ |
| Corrections Issued | 5/21/2025 | MICHAEL LOPEZ |
| Quality Review Completed | 5/23/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 8/5/2025 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/21/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 10/9/2025 | MICHAEL LOPEZ |
| Issued | 10/9/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/27/2025 | WALLIE JONG |
| Sewer availability | Cleared | 6/27/2025 | WALLIE JONG |
| CPC | Cleared | 7/29/2025 | DAMIAN GATTO |
| CPC | Cleared | 7/29/2025 | DAMIAN GATTO |
| CPC | Cleared | 7/29/2025 | DAMIAN GATTO |
| HPOZ | Cleared | 7/29/2025 | DAMIAN GATTO |
| Hydrant and Access approval | Cleared | 7/29/2025 | KURT CORRAL |
| Construction near power lines | Cleared | 7/30/2025 | RIDWAN HARDY |
| HPOZ | Cleared | 10/8/2025 | DAMIAN GATTO |
Contact Information
| Architect | Davis,, Paul S; Lic. No.: NA27920 | , |
| Contractor | Owner-Builder | , |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/11/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 10/11/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 11/5/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 11/5/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Corrections Issued | JEFFREY MEAD |
| Deputy Wood Construction | 11/13/2025 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2025 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 11/21/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 11/24/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/10/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 12/10/2025 | Approved | JEFFREY MEAD |
| Sewer | 12/10/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Sewer | 12/15/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 12/17/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 12/17/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 12/17/2025 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 12/17/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/6/2026 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 3/6/2026 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/16/2026 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/16/2026 | Approved | JEFFREY MEAD |
| Insulation | 3/20/2026 | Approved | JEFFREY MEAD |
| Drywall Nailing | 3/24/2026 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 4/7/2026 | Approved | JOSH MEISTER |