232 1/2 S WINDSOR BLVD 90004

Certificate Information: 232 1/2 S WINDSOR BLVD 90004

Application / Permit
25010-10000-01988
Plan Check / Job No.
B25LA18444
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. PROPOSED 2-STORY DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE. GROUND FLOOR WILL CONTAIN RECREATION ROOM AND GARAGE AND SECOND FLOOR WILL BE ADU.
Permit Issued
Issued on 10/9/2025
Issuing Office
Current Status
Issued on 10/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/8/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 MICHAEL LOPEZ
Corrections Issued 5/21/2025 MICHAEL LOPEZ
Quality Review Completed 5/23/2025 PRANITA SHAH
Applicant returned to address corrections 8/5/2025 MICHAEL LOPEZ
Applicant returned to address corrections 8/21/2025 MICHAEL LOPEZ
Plan Check Approved 10/9/2025 MICHAEL LOPEZ
Issued 10/9/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/27/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/27/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 6/27/2025 WALLIE JONG
Sewer availability Cleared 6/27/2025 WALLIE JONG
CPC Cleared 7/29/2025 DAMIAN GATTO
CPC Cleared 7/29/2025 DAMIAN GATTO
CPC Cleared 7/29/2025 DAMIAN GATTO
HPOZ Cleared 7/29/2025 DAMIAN GATTO
Hydrant and Access approval Cleared 7/29/2025 KURT CORRAL
Construction near power lines Cleared 7/30/2025 RIDWAN HARDY
HPOZ Cleared 10/8/2025 DAMIAN GATTO

Contact Information

Architect Davis,, Paul S; Lic. No.: NA27920       ,
Contractor Owner-Builder       ,
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/11/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 10/11/2025 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 11/5/2025 Approved JEFFREY MEAD
Underground Mechanical 11/5/2025 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Corrections Issued JEFFREY MEAD
Deputy Wood Construction 11/13/2025 Conditional Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 11/21/2025 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 11/21/2025 Not Ready for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Approved JEFFREY MEAD
PLUMBING-Rough 11/24/2025 Approved JEFFREY MEAD
ELECTRICAL-Rough 12/10/2025 Approved JEFFREY MEAD
HVAC-Rough 12/10/2025 Approved JEFFREY MEAD
Sewer 12/10/2025 Not Ready for Inspection JEFFREY MEAD
Sewer 12/15/2025 Approved ALEX COLIN
BUILDING-Rough-Frame 12/17/2025 Corrections Issued JEFFREY MEAD
Green Building Rough 12/17/2025 Not Ready for Inspection JEFFREY MEAD
METHANE-Rough 12/17/2025 Approved JEFFREY MEAD
Verify Sprinkler Sign Off 12/17/2025 Approved JEFFREY MEAD
BUILDING-Rough-Frame 3/6/2026 Corrections Issued JEFFREY MEAD
Green Building Rough 3/6/2026 Approved JEFFREY MEAD
BUILDING-Rough-Frame 3/16/2026 Approved JEFFREY MEAD
Interior/Exterior Lathing 3/16/2026 Approved JEFFREY MEAD
Insulation 3/20/2026 Approved JEFFREY MEAD
Drywall Nailing 3/24/2026 Approved JEFFREY MEAD
Interior/Exterior Lathing 4/7/2026 Approved JOSH MEISTER