1118 N CHARM ACRES PL 90272

Certificate Information: 1118 N CHARM ACRES PL 90272

Application / Permit
25010-10000-01984
Plan Check / Job No.
B25LA18416
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND BASEMENT, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 7/9/2025
Issuing Office
Current Status
Issued on 7/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/8/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 VIVIAN LAO
Corrections Issued 5/12/2025 VIVIAN LAO
Quality Review Completed 5/12/2025 JOHN FRANCIA
Applicant returned to address corrections 6/25/2025 VIVIAN LAO
Applicant returned to address corrections 7/7/2025 VIVIAN LAO
Plan Check Approved 7/8/2025 VIVIAN LAO
Issued 7/9/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/30/2025 DAVID PEREZ
Roof/Waste drainage to street Cleared 5/30/2025 DAVID PEREZ
Sewer availability Cleared 5/30/2025 DAVID PEREZ
Hydrant and Access approval Cleared 6/4/2025 PATRICK PEREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 7/17/2025 Partial Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 8/5/2025 Partial Approval BOBBY KEY
Underground Mechanical 8/27/2025 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 9/9/2025 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 9/16/2025 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 9/23/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 10/20/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Partial Approval TEMISTOCLES CAAL
Deputy Wood Construction 12/8/2025 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 1/6/2026 Partial Approval DANIEL VERA
Pre-Inspection 1/26/2026 Partial Inspection TEMISTOCLES CAAL
Interior/Exterior Lathing 2/3/2026 Partial Approval DANIEL VERA
PLUMBING-Final 2/3/2026 Corrections Issued DANIEL VERA
PLUMBING-Rough 2/3/2026 Approved DANIEL VERA
ELECTRICAL-Rough 2/9/2026 Approved TEMISTOCLES CAAL
HVAC-Rough 2/9/2026 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/10/2026 Approved TEMISTOCLES CAAL
Green Building Rough 2/10/2026 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 2/10/2026 Approved TEMISTOCLES CAAL
HVAC-Rough 2/12/2026 Approved TEMISTOCLES CAAL
Insulation 2/17/2026 Conditional Approval MICHAEL ALLEN
Drywall Nailing 2/23/2026 Approved DANIEL VERA
Shower Pan 3/6/2026 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 3/16/2026 Approved DANIEL VERA
Pre-Inspection 5/29/2026 Partial Approval TEMISTOCLES CAAL
Sewer 5/29/2026 Approved TEMISTOCLES CAAL
Underground Mechanical 5/29/2026 Approved TEMISTOCLES CAAL
Underground Mechanical 7/15/2026 Corrections Issued JESUS PINEDA