626 N LAS CASAS AVE 90272

Certificate Information: 626 N LAS CASAS AVE 90272

Application / Permit
25010-10000-01978
Plan Check / Job No.
B25LA18275
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, JR-ADU per GC 66323(a)(1) and 66333.
Permit Issued
Issued on 7/11/2025
Issuing Office
Current Status
Issued on 7/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/21/2025 APPLICANT
Assigned to Plan Check Engineer 5/22/2025 JOHNNY WU
Corrections Issued 5/23/2025 JOHNNY WU
Quality Review Completed 5/29/2025 JOSE RODRIGUEZ
Applicant returned to address corrections 6/12/2025 JOHNNY WU
Applicant returned to address corrections 6/17/2025 JOHNNY WU
Applicant returned to address corrections 6/25/2025 JOHNNY WU
Applicant returned to address corrections 7/3/2025 JOHNNY WU
Applicant returned to address corrections 7/8/2025 JOHNNY WU
Plan Check Approved 7/10/2025 JOHNNY WU
Issued 7/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/28/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 6/2/2025 JESUS CISNEROS
Sewer availability Cleared 6/2/2025 JESUS CISNEROS
Low Impact Development (LID) Cleared 6/5/2025 MITESH PATEL
Roof/Waste drainage to street Cleared 6/9/2025 LIAM ODONOVAN
Hydrant and Access approval Cleared 6/10/2025 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Balan,, Mark Hari; Lic. No.: CS4808 19871 YORBA LINDA BLVD   SUITE 105    YORBA LINDA, CA 92886

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/12/2025 Corrections Issued BOBBY KEY
PLUMBING-Rough 8/14/2025 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 8/26/2025 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Approved STEPHANIE SWANSON
PLUMBING-Rough 10/7/2025 Approved MEL KHACHATOURIAN
HVAC-Rough 10/21/2025 Corrections Issued KENNETH NAGLE
HVAC-Rough 10/23/2025 Partial Approval MEL KHACHATOURIAN
Shower Pan 10/23/2025 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 10/28/2025 Approved MEL KHACHATOURIAN
HVAC-Rough 10/28/2025 Approved MEL KHACHATOURIAN
Shower Pan 10/28/2025 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Not Ready for Inspection MEL KHACHATOURIAN
Sewer 11/13/2025 Approved MEL KHACHATOURIAN
Underground Mechanical 11/13/2025 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 11/17/2025 Conditional Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/17/2025 Partial Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 11/24/2025 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 11/26/2025 Approved BOBBY KEY
Footing/Foundation/Slab 11/26/2025 Approved BOBBY KEY
Green Building Rough 11/26/2025 Approved BOBBY KEY
Special/Order Compliance 11/26/2025 Corrections Issued BOBBY KEY
Verify Sprinkler Sign Off 11/26/2025 Approved BOBBY KEY
Insulation 12/3/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 12/9/2025 Approved DANIEL VERA
Drywall Nailing 12/24/2025 Approved MEL KHACHATOURIAN
Underground Mechanical 3/3/2026 Partial Approval MEL KHACHATOURIAN
PLUMBING-Final 3/27/2026 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 4/1/2026 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 4/1/2026 Approved STEPHANIE SWANSON
ELECTRICAL-Final 4/8/2026 Not Ready for Inspection MEL KHACHATOURIAN
Final 4/8/2026 Corrections Issued MEL KHACHATOURIAN
Green Building Final 4/8/2026 Approved MEL KHACHATOURIAN
HVAC-Final 4/8/2026 Partial Approval MEL KHACHATOURIAN
PLUMBING-Final 4/8/2026 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV No Gas MEL KHACHATOURIAN
Service/Power Release 4/8/2026 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 4/8/2026 Approved MEL KHACHATOURIAN