6235 1/4 W BANNER AVE 90038
Certificate Information: 6235 1/4 W BANNER AVE 90038
- Application / Permit
- 25010-10000-01968
- Plan Check / Job No.
- B25LA18233
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan CONSTRUCT NEW 2 STORY DETACHED ADU GC 66323(a)(4) AND PER ENGINEER DESIGN 1 OF 2
- Permit Issued
- Issued on 8/24/2025
- Issuing Office
- Current Status
- CofO Issued on 5/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | JOSEPH RAFOLS |
| Corrections Issued | 6/4/2025 | JOSEPH RAFOLS |
| Quality Review Completed | 6/12/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 8/7/2025 | JOSEPH RAFOLS |
| Plan Check Approved | 8/21/2025 | JOSEPH RAFOLS |
| Issued | 8/24/2025 | APPLICANT |
| CofO in Progress | 5/20/2026 | CRAIG VAUGHAN |
| Permit Finaled | 5/21/2026 | DEROLD HAUFF |
| CofO Issued | 5/21/2026 | DEROLD HAUFF |
| Permit Finaled | 5/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 6/14/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2025 | CINDY QI |
| Sewer availability | Cleared | 6/17/2025 | CINDY QI |
| Construction near power lines | Cleared | 8/5/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/30/2025 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 9/30/2025 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 10/1/2025 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/9/2025 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/9/2025 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/22/2025 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2025 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 11/24/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/24/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/1/2025 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/1/2025 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 12/1/2025 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/1/2025 | Partial Approval | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 12/1/2025 | Approved | CRAIG VAUGHAN |
| Insulation | 12/4/2025 | Approved | CRAIG VAUGHAN |
| Shower Pan | 12/4/2025 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 12/9/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/16/2025 | Approved | ROY SPAULDING |
| Special/Order Compliance | 1/5/2026 | Partial Inspection | SCOTT FINNILA |
| Underground Mechanical | 2/26/2026 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 3/26/2026 | Partial Inspection | SCOTT FINNILA |
| Final | 4/10/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 4/10/2026 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 4/10/2026 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 4/10/2026 | Approved | CRAIG VAUGHAN |
| Final | 4/20/2026 | OK to Issue CofO | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Not Required | CRAIG VAUGHAN |
| Service/Power Release | 4/20/2026 | Approved | CRAIG VAUGHAN |