17952 W TRAMONTO DR 90272

Certificate Information: 17952 W TRAMONTO DR 90272

Application / Permit
25010-10000-01956
Plan Check / Job No.
B25LA18050
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE,
Permit Issued
Issued on 10/7/2025
Issuing Office
Current Status
Issued on 10/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/7/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 KEVIN MORALES
Corrections Issued 5/14/2025 KEVIN MORALES
Quality Review Completed 5/15/2025 EUGENE BARBEAU
Plan Check Approved 9/26/2025 KEVIN MORALES
Issued 10/7/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/6/2025 VISHAL MANDALIA
Eng Process Fee Ord 176,300 Cleared 6/6/2025 VISHAL MANDALIA
Sewer availability Cleared 6/6/2025 VISHAL MANDALIA
Roof/Waste drainage to street Cleared 6/9/2025 VISHAL MANDALIA
Hydrant and Access approval Cleared 6/17/2025 JERRY KAO

Contact Information

Contractor Denton Developments Inc; Lic. No.: 939901-B       ,

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/28/2025 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 11/13/2025 Partial Approval KENNETH NAGLE
Deputy Reinf. Concrete 11/14/2025 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 12/5/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Partial Approval BOBBY KEY
Deputy Wood Construction 2/25/2026 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 3/6/2026 Approved BOBBY KEY
Deputy Wood Construction 3/12/2026 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/25/2026 Corrections Issued DANIEL VERA
HVAC-Rough 4/13/2026 Partial Approval BOBBY KEY
HVAC-Rough 4/22/2026 Approved BOBBY KEY
ELECTRICAL-Rough 5/4/2026 Conditional Approval DANIEL VERA
Wood Frame 5/4/2026 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 5/6/2026 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 5/20/2026 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Rough 5/20/2026 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 6/3/2026 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 6/3/2026 Approved MICHAEL ALLEN
Green Building Rough 6/3/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 6/3/2026 Partial Approval MICHAEL ALLEN
Verify Sprinkler Sign Off 6/3/2026 Approved MICHAEL ALLEN
Insulation 6/18/2026 Conditional Approval ARAM AVEDISIAN