521 N SWARTHMORE AVE 90272

Certificate Information: 521 N SWARTHMORE AVE 90272

Application / Permit
25010-10000-01905
Plan Check / Job No.
B25LA17653
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (N) 1-STORY, FACTORY-BUILT, STATE-APPROVED
Permit Issued
Issued on 5/23/2025
Issuing Office
Current Status
CofO Issued on 3/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 JOHNNY WU
Corrections Issued 5/9/2025 JOHNNY WU
Quality Review Completed 5/15/2025 JOSE RODRIGUEZ
Applicant returned to address corrections 5/20/2025 JOHNNY WU
Applicant returned to address corrections 5/21/2025 JOHNNY WU
Plan Check Approved 5/21/2025 JOHNNY WU
No Progress 5/21/2025 JOHNNY WU
Plan Check Approved 5/21/2025 JOHNNY WU
Issued 5/23/2025 APPLICANT
TCO Issued (Expire Date: 07-06-2026) 1/7/2026 RICHARD STEINBACH
CofO in Progress 3/13/2026 JUAN VALENZUELA
Permit Finaled 3/13/2026 RICHARD STEINBACH
CofO Issued 3/13/2026 RICHARD STEINBACH
Permit Finaled 3/13/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/9/2025 VISHAL MANDALIA
Permit Cleared 5/14/2025 VISHAL MANDALIA
Sewer availability Cleared 5/14/2025 VISHAL MANDALIA
Low Impact Development (LID) Cleared 5/16/2025 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/16/2025 VISHAL MANDALIA
Hydrant and Access approval Cleared 5/19/2025 JERRY KAO

Contact Information

Contractor Cover Building Technologies; Lic. No.: 1039029-B       ,
Contractor Cover Technologies Inc; Lic. No.: 1039029-B       ,
Engineer Nielsen,, Gregory Michael Wat; Lic. No.: S6653 4991 WESTPARK DR      NORTH HOLLYWOOD, CA 91601

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/22/2025 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 7/22/2025 Approved TEMISTOCLES CAAL
Underground Mechanical 11/19/2025 Not Ready for Inspection STEPHANIE SWANSON
Underground Mechanical 11/26/2025 Approved STEPHANIE SWANSON
Posting Pre-Inspection 12/9/2025 Partial Inspection KENNETH NAGLE
Sewer 12/20/2025 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 12/31/2025 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 1/7/2026 Approved KENNETH NAGLE
Drywall Nailing 1/7/2026 Approved KENNETH NAGLE
Final 1/7/2026 Conditional Approval KENNETH NAGLE
Green Building Final 1/7/2026 Approved KENNETH NAGLE
Green Building Rough 1/7/2026 Approved KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 1/7/2026 SGSOV Approved KENNETH NAGLE
Service/Power Release 1/7/2026 Approved KENNETH NAGLE
Smoke Detectors 1/7/2026 Approved KENNETH NAGLE
Verify Sprinkler Sign Off 1/7/2026 Approved KENNETH NAGLE
Final 3/12/2026 OK to Issue CofO JUAN VALENZUELA