924-926 W 75TH ST 90044
Certificate Information: 924-926 W 75TH ST 90044
- Application / Permit
- 25010-10000-01891
- Plan Check / Job No.
- B25LA17451
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN. NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE. ***SHALL BE SPRINKLERED PER NFPA 13D***
- Permit Issued
- Issued on 10/8/2025
- Issuing Office
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | MICHAEL LOPEZ |
| Assigned to Zoning Architect | 5/2/2025 | NICOLE SALEEBA |
| Corrections Issued | 5/12/2025 | MICHAEL LOPEZ |
| Quality Review Completed | 5/21/2025 | GARO TELMI |
| Plan Check Approved | 9/17/2025 | MICHAEL LOPEZ |
| No Progress | 9/18/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 10/7/2025 | MICHAEL LOPEZ |
| Issued | 10/8/2025 | APPLICANT |
| CofO in Progress | 5/20/2026 | JOHN QUINTANILLA |
| CofO Issued | 5/22/2026 | DEROLD HAUFF |
| Permit Finaled | 5/22/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 6/5/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 6/23/2025 | DAVID LOPEZ |
| Address approval | Cleared | 6/24/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 6/24/2025 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 7/2/2025 | JOHN CONNEALLY |
| SB8 RUD | Cleared | 8/8/2025 | KE ZHANG |
| Frnt yard landscape/Water mgmt | Cleared | 8/29/2025 | FIPE LEILUA |
| Zoning Plan Check | Cleared | 10/1/2025 | NICOLE SALEEBA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 11/19/2025 | Conditional Approval | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 12/8/2025 | Partial Approval | LUIS CASTRO |
| Underground Mechanical | 12/8/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Conditional Approval | JOHN QUINTANILLA |
| Insulation | 12/10/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 1/13/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Approved | JOHN QUINTANILLA |
| Pre-Inspection | 1/14/2026 | Partial Inspection | NICHOLAS LOPEZ |
| HVAC-Rough | 1/23/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 1/23/2026 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 1/26/2026 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 1/26/2026 | Approved | LUIS CASTRO |
| Green Building Rough | 1/26/2026 | Not Ready for Inspection | LUIS CASTRO |
| Verify Sprinkler Sign Off | 1/26/2026 | Not Ready for Inspection | LUIS CASTRO |
| Wood Frame | 1/27/2026 | Conditional Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 2/2/2026 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 2/2/2026 | Approved | JOHN QUINTANILLA |
| Insulation | 2/2/2026 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 2/2/2026 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 2/10/2026 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 2/10/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 4/16/2026 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 4/16/2026 | Approved | JOHN QUINTANILLA |
| Final | 4/27/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 4/27/2026 | Approved | SABAS ALONSO |
| HVAC-Final | 4/27/2026 | Approved | SABAS ALONSO |
| PLUMBING-Final | 4/27/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 4/27/2026 | Approved | SABAS ALONSO |
| Final | 5/13/2026 | Conditional Approval | JOHN QUINTANILLA |
| Service/Power Release | 5/13/2026 | Partial Inspection | JOHN QUINTANILLA |
| Final | 5/19/2026 | OK to Issue CofO | JOHN QUINTANILLA |
| Gas Test | 5/19/2026 | Approved | JOHN QUINTANILLA |