924-926 W 75TH ST 90044

Certificate Information: 924-926 W 75TH ST 90044

Application / Permit
25010-10000-01891
Plan Check / Job No.
B25LA17451
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN. NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE. ***SHALL BE SPRINKLERED PER NFPA 13D***
Permit Issued
Issued on 10/8/2025
Issuing Office
Current Status
CofO Issued on 5/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2025 APPLICANT
Assigned to Plan Check Engineer 5/1/2025 MICHAEL LOPEZ
Assigned to Zoning Architect 5/2/2025 NICOLE SALEEBA
Corrections Issued 5/12/2025 MICHAEL LOPEZ
Quality Review Completed 5/21/2025 GARO TELMI
Plan Check Approved 9/17/2025 MICHAEL LOPEZ
No Progress 9/18/2025 MICHAEL LOPEZ
Plan Check Approved 10/7/2025 MICHAEL LOPEZ
Issued 10/8/2025 APPLICANT
CofO in Progress 5/20/2026 JOHN QUINTANILLA
CofO Issued 5/22/2026 DEROLD HAUFF
Permit Finaled 5/22/2026 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 6/5/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 6/23/2025 DAVID LOPEZ
Address approval Cleared 6/24/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/24/2025 DAVID LOPEZ
Sewer availability Cleared 6/24/2025 DAVID LOPEZ
Hydrant and Access approval Cleared 7/2/2025 JOHN CONNEALLY
SB8 RUD Cleared 8/8/2025 KE ZHANG
Frnt yard landscape/Water mgmt Cleared 8/29/2025 FIPE LEILUA
Zoning Plan Check Cleared 10/1/2025 NICOLE SALEEBA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B       ,
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/12/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 11/12/2025 Approved ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 11/19/2025 Conditional Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 12/8/2025 Partial Approval LUIS CASTRO
Underground Mechanical 12/8/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Conditional Approval JOHN QUINTANILLA
Insulation 12/10/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 12/16/2025 Partial Approval SABAS ALONSO
Deputy Wood Construction 1/13/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Approved JOHN QUINTANILLA
Pre-Inspection 1/14/2026 Partial Inspection NICHOLAS LOPEZ
HVAC-Rough 1/23/2026 Approved JOHN QUINTANILLA
PLUMBING-Rough 1/23/2026 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 1/26/2026 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 1/26/2026 Approved LUIS CASTRO
Green Building Rough 1/26/2026 Not Ready for Inspection LUIS CASTRO
Verify Sprinkler Sign Off 1/26/2026 Not Ready for Inspection LUIS CASTRO
Wood Frame 1/27/2026 Conditional Approval JOHN QUINTANILLA
BUILDING-Rough-Frame 2/2/2026 Approved JOHN QUINTANILLA
Green Building Rough 2/2/2026 Approved JOHN QUINTANILLA
Insulation 2/2/2026 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 2/2/2026 Approved JOHN QUINTANILLA
Drywall Nailing 2/10/2026 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 2/10/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Final 4/16/2026 Approved JOHN QUINTANILLA
Service/Power Release 4/16/2026 Approved JOHN QUINTANILLA
Final 4/27/2026 Corrections Issued SABAS ALONSO
Green Building Final 4/27/2026 Approved SABAS ALONSO
HVAC-Final 4/27/2026 Approved SABAS ALONSO
PLUMBING-Final 4/27/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/27/2026 SGSOV Approved SABAS ALONSO
Smoke Detectors 4/27/2026 Approved SABAS ALONSO
Final 5/13/2026 Conditional Approval JOHN QUINTANILLA
Service/Power Release 5/13/2026 Partial Inspection JOHN QUINTANILLA
Final 5/19/2026 OK to Issue CofO JOHN QUINTANILLA
Gas Test 5/19/2026 Approved JOHN QUINTANILLA