905 N GALLOWAY ST 90272

Certificate Information: 905 N GALLOWAY ST 90272

Application / Permit
25010-10000-01890
Plan Check / Job No.
B25LA17450
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. 78'-0" x 30'-0". NFPA 13D SOLAR INSTALLATION REQUIRED TO MEET 3.41KW PER TITLE 24 ENERGY PRIOR TO COFO
Permit Issued
Issued on 9/2/2025
Issuing Office
Current Status
Issued on 9/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/1/2025 APPLICANT
Assigned to Plan Check Engineer 5/1/2025 VIVIAN LAO
Corrections Issued 5/6/2025 VIVIAN LAO
Quality Review Completed 5/7/2025 JOHN FRANCIA
Applicant returned to address corrections 5/28/2025 VIVIAN LAO
Plan Check Approved 6/3/2025 VIVIAN LAO
Issued 9/2/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/16/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 5/16/2025 SAFA JAVANMARDI
Sewer availability Cleared 5/16/2025 SAFA JAVANMARDI
Hydrant and Access approval Cleared 5/28/2025 GILBERT URREA
Hold Cleared 10/1/2025 MARIA VENDIVIL

Contact Information

Contractor Williamson Construction Co Inc; Lic. No.: 976074-B       ,
Engineer Shepphird,, William Reynolds; Lic. No.: C59229 PO BOX 8446      CALABASAS, CA 91372

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/8/2025 Corrections Issued MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 10/10/2025 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 10/10/2025 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 10/22/2025 Partial Approval TEMISTOCLES CAAL
Underground Mechanical 10/22/2025 Partial Approval TEMISTOCLES CAAL
Underground Mechanical 10/27/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 10/28/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Conditional Approval TEMISTOCLES CAAL
Deputy Wood Construction 2/25/2026 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 3/10/2026 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Conditional Approval MICHAEL ALLEN
ELECTRICAL-Rough 4/17/2026 Corrections Issued DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Not Ready for Inspection DANIEL VERA
Green Building Rough 4/17/2026 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 4/17/2026 Corrections Issued DANIEL VERA
Verify Sprinkler Sign Off 4/17/2026 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 5/19/2026 Approved JESUS PINEDA
HVAC-Rough 5/19/2026 Approved JESUS PINEDA
PLUMBING-Rough 5/19/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/21/2026 Approved JESUS PINEDA
Final 5/21/2026 Corrections Issued JESUS PINEDA
Green Building Rough 5/21/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 5/21/2026 Partial Approval JESUS PINEDA
Verify Sprinkler Sign Off 5/21/2026 Approved JESUS PINEDA
Insulation 5/29/2026 Corrections Issued ARAM AVEDISIAN