1044 N ILIFF ST 90272
Certificate Information: 1044 N ILIFF ST 90272
- Application / Permit
- 25010-10000-01858
- Plan Check / Job No.
- B25LA17240
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2025 WILDFIRE REBUILD **2025 Wildfire Not Eligible Project** Convert and addition rebuilt fire damage garage into a new 2-story ADU per 65852.2(e)(1)(B) and LAMC 12.22 A.33 ineligible Fire Sprinkler maintain portion of existing fdn
- Permit Issued
- Issued on 7/15/2025
- Issuing Office
- Current Status
- Issued on 7/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | KHEDER ALRAZAA |
| Corrections Issued | 5/2/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 5/6/2025 | GARO TELMI |
| Applicant returned to address corrections | 6/24/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 7/10/2025 | KHEDER ALRAZAA |
| Issued | 7/15/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Sewer availability | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Hydrant and Access approval | Cleared | 6/10/2025 | KURT CORRAL |
| Construction within easement | Cleared | 6/16/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Unified Home Solutions Inc; Lic. No.: 1137163-B | , |
| Engineer | Vahdat,, Shahram; Lic. No.: C47934 | 14560 BENEFIT STREET UNIT 301 SHERMAN OAKS, CA 91403 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/19/2025 | Partial Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 9/3/2025 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/3/2025 | Approved | TEMISTOCLES CAAL |
| Sewer | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 10/7/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Wood Construction | 11/6/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Partial Approval | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 11/19/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/3/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/3/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 2/3/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 2/3/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/3/2026 | Partial Approval | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 2/3/2026 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/6/2026 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/6/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 2/6/2026 | Approved | TEMISTOCLES CAAL |
| Insulation | 2/18/2026 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 2/27/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 2/27/2026 | Not Ready for Inspection | DANIEL VERA |
| Shower Pan | 2/27/2026 | Not Ready for Inspection | DANIEL VERA |
| Interior/Exterior Lathing | 3/18/2026 | Approved | MICHAEL ALLEN |
| Shower Pan | 3/18/2026 | Approved | MICHAEL ALLEN |