4900 1/2 E MALTA ST 90042
Certificate Information: 4900 1/2 E MALTA ST 90042
- Application / Permit
- 25010-10000-01844
- Plan Check / Job No.
- B25LA17152
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1. (N) 2-STORY ADU #1 PER STATE LAW
- Permit Issued
- Issued on 8/7/2025
- Issuing Office
- Current Status
- Issued on 8/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | JOSEPH RAFOLS |
| Corrections Issued | 6/2/2025 | JOSEPH RAFOLS |
| Quality Review Completed | 6/12/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 7/21/2025 | JOSEPH RAFOLS |
| Plan Check Approved | 8/5/2025 | JOSEPH RAFOLS |
| Issued | 8/7/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/2/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2025 | WALLIE JONG |
| Sewer availability | Cleared | 6/4/2025 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 6/16/2025 | KENNETH FRASER |
| Grading Pre-Inspection | Cleared | 7/21/2025 | JOSEPH RAFOLS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/21/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/25/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2026 | Corrections Issued | GEM DE OCAMPO |
| Wood Frame | 1/22/2026 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/9/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/9/2026 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/9/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/9/2026 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 3/9/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/6/2026 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/6/2026 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/6/2026 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/6/2026 | Partial Approval | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 4/6/2026 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 5/1/2026 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/1/2026 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/5/2026 | No Result Entered | OSVALDO PARAMO |
| Shower Pan | 6/5/2026 | No Result Entered | OSVALDO PARAMO |