4830 N NOBLE AVE 91403

Certificate Information: 4830 N NOBLE AVE 91403

Application / Permit
25010-10000-01834
Plan Check / Job No.
B25LA17055
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
Permit Issued
Issued on 9/3/2025
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2025 APPLICANT
Assigned to Plan Check Engineer 5/2/2025 GIOVANNY CHAVEZ
Corrections Issued 5/5/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 6/25/2025 GIOVANNY CHAVEZ
Plan Check Approved 6/30/2025 GIOVANNY CHAVEZ
Issued 9/3/2025 APPLICANT
CofO in Progress 5/5/2026 MICHAEL CORTEZ
Permit Finaled 5/28/2026 RUBEN SALAS
CofO Issued 5/28/2026 RUBEN SALAS
Permit Finaled 5/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/11/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/22/2025 BIAINA HARITUNIAN
Sewer availability Cleared 5/22/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 6/20/2025 GEVORK KARAPETYAN
Roof/Waste drainage to street Cleared 6/24/2025 BIAINA HARITUNIAN

Contact Information

Contractor All Building & Construction Inc; Lic. No.: 1040335-B       ,
Engineer Shmeit,, Ayman Ivan; Lic. No.: C93325 16905 ARMDORE AVE      BELLFLOWER, CA 90706

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/11/2025 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 9/18/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 11/19/2025 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 11/19/2025 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 11/19/2025 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 11/19/2025 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Rough 11/19/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 11/19/2025 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 11/19/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 11/21/2025 Approved JACK KARGODORIAN
HVAC-Rough 11/21/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/21/2025 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 11/21/2025 Approved JACK KARGODORIAN
Wood Frame 11/21/2025 Approved JACK KARGODORIAN
Insulation 12/5/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/5/2025 Partial Approval JACK KARGODORIAN
Shower Pan 12/5/2025 Not Ready for Inspection JACK KARGODORIAN
Drywall Nailing 12/15/2025 Approved JACK KARGODORIAN
Green Building Rough 12/15/2025 Approved JACK KARGODORIAN
Sewer 3/2/2026 Approved MISAEL ESPARZA
Underground Mechanical 3/2/2026 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 4/22/2026 Approved MICHAEL CORTEZ
Final 4/22/2026 Corrections Issued MICHAEL CORTEZ
Green Building Final 4/22/2026 Approved MICHAEL CORTEZ
MERV13>=Final 4/22/2026 Approved MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 4/22/2026 SGSOV Not Required MICHAEL CORTEZ
Smoke Detectors 4/22/2026 Approved MICHAEL CORTEZ
Final 5/4/2026 OK to Issue CofO MICHAEL CORTEZ
Service/Power Release 5/4/2026 Not Required MICHAEL CORTEZ