10018 N DEBRA AVE 91343

Certificate Information: 10018 N DEBRA AVE 91343

Application / Permit
25010-10000-01793
Plan Check / Job No.
B25LA16705
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ADU PER LAMC 12.22A.33(b)(1)
Permit Issued
Issued on 5/22/2025
Issuing Office
Current Status
Issued on 5/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/25/2025 APPLICANT
Assigned to Plan Check Engineer 4/30/2025 FERNANDO FLORES
Corrections Issued 5/2/2025 FERNANDO FLORES
Building Plans Picked Up 5/6/2025 APPLICANT
Plan Check Approved 5/13/2025 ZAW HAN
Issued 5/22/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/5/2025 MANUEL TEJADA
Address approval Cleared 5/7/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/7/2025 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 5/7/2025 BRYAN GODINEZ
Sewer availability Cleared 5/7/2025 BRYAN GODINEZ
GPI Written Notices Cleared 5/13/2025 MANUEL TEJADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Interior/Exterior Lathing 6/9/2026   
Drywall Nailing 6/9/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/24/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 3/4/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/9/2026 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 3/24/2026 Approved CHRISTOPHER ROJAS
Special/Order Compliance 3/24/2026 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/28/2026 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/28/2026 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 4/28/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 4/28/2026 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/26/2026 Corrections Issued JOSE AVILA
HVAC-Rough 5/26/2026 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/26/2026 Approved JOSE AVILA
BUILDING-Rough-Frame 5/28/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/28/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 5/28/2026 Approved CHRISTOPHER ROJAS
Insulation 6/2/2026 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/2/2026 Partial Approval CHRISTOPHER ROJAS