10018 N DEBRA AVE 91343
Certificate Information: 10018 N DEBRA AVE 91343
- Application / Permit
- 25010-10000-01793
- Plan Check / Job No.
- B25LA16705
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ADU PER LAMC 12.22A.33(b)(1)
- Permit Issued
- Issued on 5/22/2025
- Issuing Office
- Current Status
- Issued on 5/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2025 | FERNANDO FLORES |
| Corrections Issued | 5/2/2025 | FERNANDO FLORES |
| Building Plans Picked Up | 5/6/2025 | APPLICANT |
| Plan Check Approved | 5/13/2025 | ZAW HAN |
| Issued | 5/22/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/5/2025 | MANUEL TEJADA |
| Address approval | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Sewer availability | Cleared | 5/7/2025 | BRYAN GODINEZ |
| GPI Written Notices | Cleared | 5/13/2025 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 6/9/2026 |
| Drywall Nailing | 6/9/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/24/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 3/4/2026 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 3/9/2026 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/24/2026 | Approved | CHRISTOPHER ROJAS |
| Special/Order Compliance | 3/24/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/28/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/28/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 4/28/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 4/28/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/26/2026 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 5/26/2026 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/26/2026 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/28/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/28/2026 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 5/28/2026 | Approved | CHRISTOPHER ROJAS |
| Insulation | 6/2/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/2/2026 | Partial Approval | CHRISTOPHER ROJAS |