2015 S MANNING AVE 90025

Certificate Information: 2015 S MANNING AVE 90025

Application / Permit
25010-10000-01761
Plan Check / Job No.
B25LA16467
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED ADU PER GCS 66323(a)(2), ALL WORK PER ENG.
Permit Issued
Issued on 9/15/2025
Issuing Office
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2025 APPLICANT
Assigned to Plan Check Engineer 4/28/2025 LUISANGEL VALENZUELA
Corrections Issued 4/29/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 7/1/2025 ALEC MOUSAKHANIAN
Applicant returned to address corrections 7/24/2025 NAREG ATARIAN
Plan Check Approved 8/14/2025 NAREG ATARIAN
Issued 9/15/2025 APPLICANT
CofO in Progress 4/9/2026 RYAN SALAZAR
Permit Finaled 4/9/2026 RICHARD STEINBACH
CofO Issued 4/9/2026 RICHARD STEINBACH
Permit Finaled 4/9/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/5/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 5/5/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 5/15/2025 MICHAEL BROWN
Sewer availability Cleared 5/15/2025 MICHAEL BROWN
Specific Plan Cleared 5/23/2025 PEDRO AYALA
Grading Pre-Inspection Cleared 7/1/2025 LUISANGEL VALENZUELA
Construction near power lines Cleared 7/8/2025 RIDWAN HARDY
GPI Written Notices Cleared 7/24/2025 AL GAMBLE

Contact Information

Contractor Buildoly Inc; Lic. No.: 1134744-B       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/18/2025 Partial Approval DANIEL VERA
Sewer 9/26/2025 Approved DANIEL VERA
Underground Mechanical 9/26/2025 Partial Approval DANIEL VERA
Excavation/Setback/Form/Re-Bar 9/29/2025 Not Ready for Inspection DANIEL VERA
Underground Mechanical 9/29/2025 Partial Approval DANIEL VERA
METHANE-Subgrade 10/2/2025 Approved DANIEL VERA
Deputy Methane Barrier 10/6/2025 Conditional Approval ANDREW NAVE
Deputy Methane Barrier 10/7/2025 Approved DANIEL VERA
METHANE-Barrier 10/7/2025 Approved DANIEL VERA
Deputy Methane Barrier 10/8/2025 Conditional Approval JAYLIN GRAVITTE
Deputy Methane Barrier 10/14/2025 Conditional Approval DANIEL VERA
Deputy Methane Barrier 10/15/2025 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 10/15/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 10/15/2025 Approved MICHAEL ALLEN
METHANE-Barrier 10/16/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Approved DANIEL VERA
ELECTRICAL-Rough 11/21/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 11/21/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 11/21/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 11/26/2025 Partial Approval DANIEL VERA
HVAC-Rough 11/26/2025 Approved DANIEL VERA
PLUMBING-Rough 11/26/2025 Approved DANIEL VERA
Interior/Exterior Lathing 12/3/2025 Partial Approval DANIEL VERA
BUILDING-Rough-Frame 12/9/2025 Approved CARLOS MATAMOROS
Insulation 12/9/2025 Partial Approval CARLOS MATAMOROS
METHANE-Rough 12/9/2025 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 12/9/2025 Approved CARLOS MATAMOROS
Insulation 12/12/2025 Corrections Issued CHRISTOPHER WILSON
Insulation 12/16/2025 Approved DANIEL VERA
Drywall Nailing 12/23/2025 Approved EVAN COOPER
Interior/Exterior Lathing 1/26/2026 Approved RYAN SALAZAR
Shower Pan 1/26/2026 Approved RYAN SALAZAR
Final 3/13/2026 Corrections Issued RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Not Required RYAN SALAZAR
Service/Power Release 3/13/2026 Approved RYAN SALAZAR
Smoke Detectors 3/13/2026 Approved RYAN SALAZAR
Final 3/31/2026 OK to Issue CofO RYAN SALAZAR