2015 S MANNING AVE 90025
Certificate Information: 2015 S MANNING AVE 90025
- Application / Permit
- 25010-10000-01761
- Plan Check / Job No.
- B25LA16467
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW DETACHED ADU PER GCS 66323(a)(2), ALL WORK PER ENG.
- Permit Issued
- Issued on 9/15/2025
- Issuing Office
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/29/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 7/1/2025 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 7/24/2025 | NAREG ATARIAN |
| Plan Check Approved | 8/14/2025 | NAREG ATARIAN |
| Issued | 9/15/2025 | APPLICANT |
| CofO in Progress | 4/9/2026 | RYAN SALAZAR |
| Permit Finaled | 4/9/2026 | RICHARD STEINBACH |
| CofO Issued | 4/9/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/9/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/5/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 5/5/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/15/2025 | MICHAEL BROWN |
| Specific Plan | Cleared | 5/23/2025 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 7/1/2025 | LUISANGEL VALENZUELA |
| Construction near power lines | Cleared | 7/8/2025 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 7/24/2025 | AL GAMBLE |
Contact Information
| Contractor | Buildoly Inc; Lic. No.: 1134744-B | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/18/2025 | Partial Approval | DANIEL VERA |
| Sewer | 9/26/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 9/26/2025 | Partial Approval | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 9/29/2025 | Not Ready for Inspection | DANIEL VERA |
| Underground Mechanical | 9/29/2025 | Partial Approval | DANIEL VERA |
| METHANE-Subgrade | 10/2/2025 | Approved | DANIEL VERA |
| Deputy Methane Barrier | 10/6/2025 | Conditional Approval | ANDREW NAVE |
| Deputy Methane Barrier | 10/7/2025 | Approved | DANIEL VERA |
| METHANE-Barrier | 10/7/2025 | Approved | DANIEL VERA |
| Deputy Methane Barrier | 10/8/2025 | Conditional Approval | JAYLIN GRAVITTE |
| Deputy Methane Barrier | 10/14/2025 | Conditional Approval | DANIEL VERA |
| Deputy Methane Barrier | 10/15/2025 | Approved | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 10/15/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 10/15/2025 | Approved | MICHAEL ALLEN |
| METHANE-Barrier | 10/16/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Rough | 11/21/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 11/21/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 11/21/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 11/26/2025 | Partial Approval | DANIEL VERA |
| HVAC-Rough | 11/26/2025 | Approved | DANIEL VERA |
| PLUMBING-Rough | 11/26/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 12/3/2025 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 12/9/2025 | Approved | CARLOS MATAMOROS |
| Insulation | 12/9/2025 | Partial Approval | CARLOS MATAMOROS |
| METHANE-Rough | 12/9/2025 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 12/9/2025 | Approved | CARLOS MATAMOROS |
| Insulation | 12/12/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Insulation | 12/16/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 12/23/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/26/2026 | Approved | RYAN SALAZAR |
| Shower Pan | 1/26/2026 | Approved | RYAN SALAZAR |
| Final | 3/13/2026 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 3/13/2026 | Approved | RYAN SALAZAR |
| Smoke Detectors | 3/13/2026 | Approved | RYAN SALAZAR |
| Final | 3/31/2026 | OK to Issue CofO | RYAN SALAZAR |