1107 N ILIFF ST 90272
Certificate Information: 1107 N ILIFF ST 90272
- Application / Permit
- 25010-10000-01757
- Plan Check / Job No.
- B25LA16430
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING. NFPA 13(D) SPRINKLERS THROUGHOUT. EO1
- Permit Issued
- Issued on 7/28/2025
- Issuing Office
- Current Status
- Issued on 7/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2025 | KEVIN MORALES |
| Corrections Issued | 5/1/2025 | KEVIN MORALES |
| Quality Review Completed | 5/1/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/9/2025 | KEVIN MORALES |
| Plan Check Approved | 7/22/2025 | KEVIN MORALES |
| Issued | 7/28/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/20/2025 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2025 | JILVER MAZARIEGOS |
| Roof/Waste drainage to street | Cleared | 6/3/2025 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 6/3/2025 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Allbright Construction & Development Inc; Lic. No.: 992248-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/28/2025 | Partial Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 9/25/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Sewer | 9/25/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/26/2025 | Partial Approval | TEMISTOCLES CAAL |
| Pre-Inspection | 9/26/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Sewer | 9/26/2025 | Partial Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 9/30/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 10/20/2025 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/20/2025 | Approved | TEMISTOCLES CAAL |
| Sewer | 10/29/2025 | No Access for Inspection | TEMISTOCLES CAAL |
| Sewer | 10/31/2025 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 10/31/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2025 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 1/13/2026 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 1/13/2026 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/13/2026 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/20/2026 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/24/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 2/24/2026 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 2/24/2026 | Approved | TEMISTOCLES CAAL |
| Insulation | 3/10/2026 | Partial Approval | RYAN SALAZAR |
| Insulation | 3/13/2026 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/18/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/30/2026 | Approved | HERBERT GIRON |
| Shower Pan | 4/30/2026 | Approved | HERBERT GIRON |