16738 W BOLLINGER DR 90272
Certificate Information: 16738 W BOLLINGER DR 90272
- Application / Permit
- 25010-10000-01720
- Plan Check / Job No.
- B25LA16062
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SOLAR INSTALLATION REQUIRED TO MEET KW PER TITLE 24 PRIOR TO COFO.
- Permit Issued
- Issued on 7/7/2025
- Issuing Office
- Current Status
- Issued on 7/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | VIVIAN LAO |
| Corrections Issued | 4/28/2025 | VIVIAN LAO |
| Quality Review Completed | 4/29/2025 | JOHN FRANCIA |
| Applicant returned to address corrections | 5/28/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 6/3/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 6/6/2025 | VIVIAN LAO |
| Plan Check Approved | 7/7/2025 | VIVIAN LAO |
| Issued | 7/7/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 6/9/2025 | CINDY QI |
| Sewer availability | Cleared | 6/9/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 6/13/2025 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: NA87383 | , |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/2/2025 | Conditional Approval | BOBBY KEY |
| Grounding or Bonding | 10/2/2025 | Conditional Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 10/17/2025 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 10/31/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 12/4/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 12/23/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Corrections Issued | DANIEL VERA |
| Green Building Rough | 12/23/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 4/21/2026 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 4/22/2026 | Partial Approval | BOBBY KEY |
| Gas Test | 5/26/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 5/26/2026 | Conditional Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 6/3/2026 | Corrections Issued | DANIEL VERA |
| Green Building Rough | 6/3/2026 | Approved | DANIEL VERA |
| Verify Sprinkler Sign Off | 6/3/2026 | Approved | DANIEL VERA |