4113 S MOORE ST 90066

Certificate Information: 4113 S MOORE ST 90066

Application / Permit
25010-10000-01691
Plan Check / Job No.
B25LA15795
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: New two story detachted ADU per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 7/1/2025
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 JESSE VIDUYA
Corrections Issued 5/21/2025 JESSE VIDUYA
Quality Review Completed 5/28/2025 CHAD DOI
Applicant returned to address corrections 6/26/2025 JESSE VIDUYA
Plan Check Approved 6/30/2025 JESSE VIDUYA
Issued 7/1/2025 APPLICANT
CofO in Progress 12/26/2025 WILBER ROSALES
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/6/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/6/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/6/2025 LEE GUILBEAUX
Sewer availability Cleared 6/6/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/6/2025 LEE GUILBEAUX
Specific Plan Cleared 6/13/2025 JOSHUA JONES
Construction near power lines Cleared 6/14/2025 TINA MIRANDA

Contact Information

Contractor Magnano Robert E Incorporated; Lic. No.: 590032-B       ,
Engineer Yu,, Irene; Lic. No.: NA68382       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/31/2025 Partial Approval WILBER ROSALES
Footing/Foundation/Slab 8/5/2025 Approved WILBER ROSALES
Underground Mechanical 8/5/2025 Approved WILBER ROSALES
PLUMBING-Rough 9/9/2025 Approved MICHAEL ALLEN
Sewer 9/9/2025 Approved MICHAEL ALLEN
Special/Order Compliance 9/9/2025 Corrections Issued MICHAEL ALLEN
Underground Mechanical 9/9/2025 Partial Approval MICHAEL ALLEN
Deputy Wood Construction 9/15/2025 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 9/22/2025 Approved JESUS RODRIGUEZ
Shower Pan 9/25/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 9/26/2025 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 9/29/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 9/29/2025 Partial Approval WILBER ROSALES
Green Building Rough 9/29/2025 Approved WILBER ROSALES
Verify Sprinkler Sign Off 9/29/2025 Approved WILBER ROSALES
Insulation 10/1/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 10/3/2025 Approved RUBEN RIVAS
Drywall Nailing 10/8/2025 Approved WILBER ROSALES
Underground Mechanical 10/28/2025 Approved WILBER ROSALES
ELECTRICAL-Final 12/4/2025 Approved WILBER ROSALES
Final 12/11/2025 Not Ready for Inspection WILBER ROSALES
Green Building Final 12/11/2025 Not Ready for Inspection WILBER ROSALES
HVAC-Final 12/11/2025 Not Ready for Inspection WILBER ROSALES
PLUMBING-Final 12/11/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Not Ready WILBER ROSALES
Service/Power Release 12/11/2025 Partial Approval WILBER ROSALES
Smoke Detectors 12/11/2025 Approved WILBER ROSALES
Final 12/24/2025 OK to Issue CofO WILBER ROSALES
Green Building Final 12/24/2025 Approved WILBER ROSALES
HVAC-Final 12/24/2025 Approved WILBER ROSALES
PLUMBING-Final 12/24/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Approved WILBER ROSALES
Service/Power Release 12/24/2025 Approved WILBER ROSALES