3229-3229 1/2 E 3RD ST 90063
Certificate Information: 3229-3229 1/2 E 3RD ST 90063
- Application / Permit
- 25010-10000-01589
- Plan Check / Job No.
- B25LA14661
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Proposed 2-story detached two ADU's per GC 66323(a)(4)
- Permit Issued
- Issued on 8/20/2025
- Issuing Office
- Current Status
- Issued on 8/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | JESSE VIDUYA |
| Corrections Issued | 5/9/2025 | JESSE VIDUYA |
| Quality Review Completed | 5/20/2025 | CHAD DOI |
| Applicant returned to address corrections | 7/18/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 7/29/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 8/8/2025 | JESSE VIDUYA |
| Plan Check Approved | 8/19/2025 | JESSE VIDUYA |
| Issued | 8/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/29/2025 | MICHAEL BROWN |
| Low Impact Development (LID) | Cleared | 6/9/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 6/14/2025 | JEREMY CHOK |
| Construction near power lines | Cleared | 7/12/2025 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 8/8/2025 | JESSE VIDUYA |
| Grading Pre-Inspection | Cleared | 8/8/2025 | RAMAZANALI ALMASI |
Contact Information
| Contractor | Bpc Development Inc; Lic. No.: 1059885-B | , |
| Contractor | Builder Point Construction; Lic. No.: 1059885-B | , |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Gas Test | 6/8/2026 |
| Service/Power Release | 6/8/2026 |
| ELECTRICAL-Final | 6/8/2026 |
| Final | 6/8/2026 |
| Smoke Detectors | 6/8/2026 |
| Drywall Nailing | 6/8/2026 |
| Green Building Final | 6/8/2026 |
| SGSOV-Seismic Gas S/O Valve | 6/8/2026 |
| BUILDING-Rough-Frame | 6/8/2026 |
Inspection Request History
| PLUMBING-Rough | 9/8/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/18/2025 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 9/18/2025 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 9/18/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 10/3/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 10/9/2025 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Approved | DEVON JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Partial Approval | JUSTIN HAWLEY |
| Special/Order Compliance | 10/22/2025 | Corrections Issued | JUSTIN HAWLEY |
| Underground Mechanical | 11/10/2025 | No Access for Inspection | FREDDIE RIVERA |
| Underground Mechanical | 11/18/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2025 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/6/2026 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 1/6/2026 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 1/6/2026 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 1/6/2026 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/6/2026 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2026 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 1/15/2026 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/20/2026 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 1/20/2026 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 1/23/2026 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 1/27/2026 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 2/2/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 2/2/2026 | Approved | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 2/3/2026 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 5/26/2026 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 5/26/2026 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 6/5/2026 | No Result Entered | FREDDIE RIVERA |
| PLUMBING-Final | 6/5/2026 | No Result Entered | FREDDIE RIVERA |