1388 W 3RD ST 90732
Certificate Information: 1388 W 3RD ST 90732
- Application / Permit
- 25010-10000-01560
- Plan Check / Job No.
- B25LA14390
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New 2 story detached accessory structure. Non conditioned storage and 2 car garage on 1st floor. ADU per LAMC 12.22A.33(b)(1) on the 2nd floor.
- Permit Issued
- Issued on 9/9/2025
- Issuing Office
- Current Status
- Issued on 9/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | MARCELA FRANQUEZ |
| Corrections Issued | 5/13/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 6/2/2025 | CHAD DOI |
| Applicant returned to address corrections | 7/18/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 8/20/2025 | MARCELA FRANQUEZ |
| Issued | 9/9/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/19/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 5/20/2025 | MICHAEL BROWN |
| Grading Pre-Inspection | Cleared | 7/18/2025 | MARCELA FRANQUEZ |
| GPI Written Notices | Cleared | 8/1/2025 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Guerra Homes Inc; Lic. No.: 1101761-B | , |
| Engineer | Namvar,, Mohammad Alipour; Lic. No.: C39797 | 231 VISTA DEL MAR STE D REDONDO BEACH, CA 90277 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/15/2025 | Partial Inspection | JOSEPH MCGARRY |
| Underground Mechanical | 10/15/2025 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 10/23/2025 | Conditional Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/23/2025 | Conditional Approval | JOSEPH MCGARRY |
| Grounding or Bonding | 10/23/2025 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 1/27/2026 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 1/27/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 2/11/2026 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 2/11/2026 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 2/11/2026 | Corrections Issued | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 2/18/2026 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2026 | Approved | JOSEPH MCGARRY |
| Gas Test | 2/18/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/18/2026 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/18/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/23/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 2/26/2026 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/4/2026 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 3/4/2026 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/4/2026 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 3/4/2026 | Approved | JOSEPH MCGARRY |
| Insulation | 3/11/2026 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 3/19/2026 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/21/2026 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/24/2026 | Approved | JOSEPH MCGARRY |
| Shower Pan | 4/24/2026 | Approved | JOSEPH MCGARRY |
| Gas Test | 6/1/2026 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/3/2026 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 6/3/2026 | Partial Approval | JOSEPH MCGARRY |