1613 N BROAD AVE 90744

Certificate Information: 1613 N BROAD AVE 90744

Application / Permit
25010-10000-01552
Plan Check / Job No.
B25LA14336
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Build new one story detached A.D.U. (22x'20') per ordinance. All work to be done per engineered design.
Permit Issued
Issued on 6/4/2025
Issuing Office
Current Status
CofO Issued on 5/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 NGHI SU
Corrections Issued 4/19/2025 NGHI SU
Plan Check Approved 6/4/2025 NGHI SU
Issued 6/4/2025 APPLICANT
CofO in Progress 5/8/2026 JOSEPH MCGARRY
Permit Finaled 5/8/2026 ANSON MAGLASANG
CofO Issued 5/8/2026 ANSON MAGLASANG
Permit Finaled 5/8/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 4/21/2025 CINDY QI
Roof/Waste drainage to street Cleared 4/21/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 4/22/2025 CINDY QI
Sewer availability Cleared 4/22/2025 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766
Geologist Kaligi,, Adam Azad; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/25/2025 Corrections Issued BEN MOLSTAD
METHANE-Barrier 8/25/2025 Not Ready for Inspection BEN MOLSTAD
METHANE-Subgrade 8/25/2025 Not Ready for Inspection BEN MOLSTAD
Footing/Foundation/Slab 8/29/2025 Partial Inspection JOSEPH MCGARRY
METHANE-Barrier 8/29/2025 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 8/29/2025 Partial Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 9/5/2025 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 9/5/2025 Partial Approval EUGENE CASSIDY
Deputy Methane Barrier 9/24/2025 Partial Approval EUGENE CASSIDY
Deputy Methane Barrier 9/25/2025 Partial Approval EUGENE CASSIDY
Deputy Methane Barrier 10/2/2025 Conditional Approval ANSON MAGLASANG
Deputy Methane Barrier 10/3/2025 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 10/6/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 10/6/2025 Approved EUGENE CASSIDY
METHANE-Subgrade 10/6/2025 Approved EUGENE CASSIDY
Pre-Inspection 10/7/2025 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 10/8/2025 Approved EUGENE CASSIDY
Pre-Inspection 10/8/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/17/2025 Corrections Issued EUGENE CASSIDY
Green Building Rough 10/17/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 10/17/2025 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 10/17/2025 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/21/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 10/21/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 10/21/2025 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 10/21/2025 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 11/4/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 11/4/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 11/4/2025 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 11/4/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/19/2025 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 11/20/2025 No Access for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 11/25/2025 Partial Approval EUGENE CASSIDY
Insulation 11/25/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 12/3/2025 Approved EUGENE CASSIDY
HVAC-Rough 12/4/2025 Approved EUGENE CASSIDY
METHANE-Rough 12/4/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 12/5/2025 Approved EUGENE CASSIDY
Green Building Rough 12/5/2025 Approved EUGENE CASSIDY
Drywall Nailing 12/8/2025 Approved EUGENE CASSIDY
Insulation 12/8/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 1/22/2026 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 1/23/2026 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 1/27/2026 Approved EUGENE CASSIDY
Pre-Inspection 1/27/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/24/2026 SGSOV Not Ready JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/18/2026 SGSOV Not Ready EUGENE CASSIDY
Final 3/20/2026 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 3/20/2026 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 3/20/2026 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 3/20/2026 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/26/2026 Corrections Issued BEN MOLSTAD
Final 3/26/2026 Corrections Issued BEN MOLSTAD
Green Building Final 3/26/2026 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 3/26/2026 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 3/26/2026 Not Ready for Inspection BEN MOLSTAD
Final 5/4/2026 Corrections Issued EUGENE CASSIDY
Green Building Final 5/4/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/4/2026 SGSOV Approved EUGENE CASSIDY
Service/Power Release 5/4/2026 Not Ready for Inspection EUGENE CASSIDY
Final 5/6/2026 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 5/6/2026 Approved JOSEPH MCGARRY