710 N ILIFF ST 90272
Certificate Information: 710 N ILIFF ST 90272
- Application / Permit
- 25010-10000-01541
- Plan Check / Job No.
- B25LA14253
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY 54.7' X 40.4' NFPA 13-D
- Permit Issued
- Issued on 6/3/2025
- Issuing Office
- Current Status
- Issued on 6/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2025 | SELLA BENYAMIN |
| Corrections Issued | 4/17/2025 | SELLA BENYAMIN |
| Quality Review Completed | 4/18/2025 | STEVEN KIM |
| Applicant returned to address corrections | 5/9/2025 | SELLA BENYAMIN |
| Plan Check Approved | 5/31/2025 | SELLA BENYAMIN |
| Issued | 6/3/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/22/2025 | JERRY KAO |
| Sewer availability | Cleared | 4/23/2025 | VISHAL MANDALIA |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2025 | VISHAL MANDALIA |
| Roof/Waste drainage to street | Cleared | 4/26/2025 | VISHAL MANDALIA |
Contact Information
| Architect | Oreck,, Kevin Robert; Lic. No.: NA23895 | , |
| Contractor | Lannen Construction Inc; Lic. No.: 811038-B | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/21/2025 | Partial Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/12/2025 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 9/17/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/17/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/24/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Approved | MEL KHACHATOURIAN |
| Deputy Wood Construction | 10/21/2025 | Conditional Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 11/5/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/5/2025 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 11/7/2025 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 11/7/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 11/13/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 11/17/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 11/17/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 11/17/2025 | Partial Approval | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 11/17/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 11/25/2025 | Corrections Issued | MICHAEL ALLEN |
| Shower Pan | 11/25/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/2/2025 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 12/9/2025 | Not Ready for Inspection | HERBERT GIRON |
| Drywall Nailing | 12/12/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/12/2025 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 12/12/2025 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 12/16/2025 | Approved | TEMISTOCLES CAAL |
| Gas Test | 3/20/2026 | Approved | JESUS PINEDA |
| Sewer | 3/20/2026 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/2/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Final | 4/2/2026 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/6/2026 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 4/8/2026 | Approved | TEMISTOCLES CAAL |
| Final | 4/28/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 4/28/2026 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 4/28/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Smoke Detectors | 4/28/2026 | Approved | TEMISTOCLES CAAL |
| Final | 5/22/2026 | Conditional Approval | MICHAEL ALLEN |
| Green Building Final | 5/22/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 5/22/2026 | Approved | MICHAEL ALLEN |
| Service/Power Release | 5/22/2026 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 5/22/2026 | Approved | MICHAEL ALLEN |