3780 S MEIER ST 90066

Certificate Information: 3780 S MEIER ST 90066

Application / Permit
25010-10000-01497
Plan Check / Job No.
B25LA13739
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ALL-ELECTRIC ACCESSORY DWELLING UNIT PER LAMC12.22A.33(b)(1). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 7/2/2025
Issuing Office
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2025 APPLICANT
Assigned to Plan Check Engineer 4/11/2025 MIROOSH KHACHATOORIAN
Corrections Issued 4/14/2025 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 6/27/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 7/1/2025 MADISON O'DELL
Issued 7/2/2025 APPLICANT
CofO in Progress 2/20/2026 DAVID FEILER
Permit Finaled 4/23/2026 RICHARD STEINBACH
Permit Finaled 4/23/2026 RICHARD STEINBACH
CofO Issued 4/23/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/22/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/22/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 4/22/2025 BIAINA HARITUNIAN
Sewer availability Cleared 4/22/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 4/23/2025 LANNY MERRICK
Specific Plan Cleared 5/23/2025 PEDRO AYALA
Construction near power lines Cleared 6/21/2025 RIDWAN HARDY
Construction within easement Cleared 6/21/2025 RIDWAN HARDY

Contact Information

Contractor Dwell Homes Llc; Lic. No.: 1030158-B       ,
Contractor Dwell Homes Los Angeles; Lic. No.: 1030158-B       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 28025 DOROTHY DR STE 202      AGOURA HILLS, CA 91301

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/7/2025 Approved WILBER ROSALES
Excavation/Setback/Form/Re-Bar 8/18/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 8/18/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 9/3/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Approved WILBER ROSALES
Green Building Rough 9/3/2025 Not Ready for Inspection WILBER ROSALES
Rough-Elec/Plmb/HVAC 9/3/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 9/11/2025 Approved MICHAEL ALLEN
Green Building Rough 9/11/2025 Approved MICHAEL ALLEN
Insulation 9/11/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 9/11/2025 Approved MICHAEL ALLEN
Drywall Nailing 9/16/2025 Approved WILBER ROSALES
Shower Pan 9/16/2025 Approved WILBER ROSALES
Underground Mechanical 9/16/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 9/19/2025 Approved JAYLIN GRAVITTE
Sewer 11/20/2025 Approved WILBER ROSALES
ELECTRICAL-Final 12/4/2025 Approved SEAN HAUPT
Final 12/12/2025 Corrections Issued WILBER ROSALES
Green Building Final 12/12/2025 Approved WILBER ROSALES
HVAC-Final 12/12/2025 Approved WILBER ROSALES
PLUMBING-Final 12/12/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Not Required WILBER ROSALES
Service/Power Release 12/12/2025 Not Ready for Inspection WILBER ROSALES
Smoke Detectors 12/12/2025 Approved WILBER ROSALES
Final 1/20/2026 Partial Inspection ANTHONY EGSON
Service/Power Release 1/20/2026 Not Ready for Inspection ANTHONY EGSON
Final 1/23/2026 No Access for Inspection RUBEN RIVAS
Service/Power Release 1/23/2026 No Access for Inspection RUBEN RIVAS
Final 2/20/2026 OK to Issue CofO DAVID FEILER
Service/Power Release 2/20/2026 Approved DAVID FEILER