3921 S ALLA ROAD 90066
Certificate Information: 3921 S ALLA ROAD 90066
- Application / Permit
- 25010-10000-01454
- Plan Check / Job No.
- B25LA13272
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New 1-story detached ADU per State GC 66323(a)(2). Design per licensed engineer.
- Permit Issued
- Issued on 7/2/2025
- Issuing Office
- Current Status
- CofO Issued on 4/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2025 | HOOMAN HAJIZADEH |
| Corrections Issued | 4/10/2025 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 5/2/2025 | CAROLEAN BASMA |
| Plan Check Approved | 5/7/2025 | CAROLEAN BASMA |
| Issued | 7/2/2025 | APPLICANT |
| CofO in Progress | 4/27/2026 | DAKOTA LOW |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
| CofO Issued | 4/28/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/23/2025 | OSCAR CASTRO |
| Address approval | Cleared | 4/24/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/24/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/24/2025 | BIAINA HARITUNIAN |
| Specific Plan | Cleared | 5/1/2025 | RICHARD WOO |
Contact Information
| Architect | Verdugo,, Emilio Amado; Lic. No.: NA33263 | , |
| Contractor | U S Home Developers Inc; Lic. No.: 947505-B | , |
| Contractor | Us Home Developers Inc; Lic. No.: 947505-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/29/2025 | Corrections Issued | WILBER ROSALES |
| Footing/Foundation/Slab | 7/31/2025 | Approved | WILBER ROSALES |
| Underground Mechanical | 7/31/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 10/14/2025 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Rough | 10/14/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 10/14/2025 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Rough | 10/14/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Rough | 10/14/2025 | Corrections Issued | WILBER ROSALES |
| BUILDING-Rough-Frame | 10/16/2025 | Conditional Approval | WILBER ROSALES |
| HVAC-Rough | 10/16/2025 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 10/16/2025 | Corrections Issued | WILBER ROSALES |
| Insulation | 10/27/2025 | Corrections Issued | RUBEN RIVAS |
| Interior/Exterior Lathing | 10/27/2025 | Partial Approval | RUBEN RIVAS |
| Insulation | 10/29/2025 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 11/3/2025 | Partial Approval | WILBER ROSALES |
| Green Building Rough | 11/3/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 11/3/2025 | Approved | WILBER ROSALES |
| Shower Pan | 11/3/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 2/18/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 2/18/2026 | Approved | ANTHONY EGSON |
| Final | 2/18/2026 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 2/18/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 2/18/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 2/18/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/19/2026 | Not Ready for Inspection | DAKOTA LOW |
| Final | 3/19/2026 | Corrections Issued | DAKOTA LOW |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Approved | DAKOTA LOW |
| Service/Power Release | 3/19/2026 | Not Ready for Inspection | DAKOTA LOW |
| BUILDING-Rough-Frame | 4/10/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/10/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Final | 4/10/2026 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 4/10/2026 | Conditional Approval | MICHAEL ALLEN |
| PLUMBING-Final | 4/10/2026 | Approved | MICHAEL ALLEN |
| Service/Power Release | 4/10/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/23/2026 | Approved | DAKOTA LOW |
| Final | 4/23/2026 | OK to Issue CofO | DAKOTA LOW |
| HVAC-Final | 4/23/2026 | Approved | DAKOTA LOW |
| Service/Power Release | 4/23/2026 | Approved | DAKOTA LOW |