1012 N DEXTER ST 90042

Certificate Information: 1012 N DEXTER ST 90042

Application / Permit
25010-10000-01451
Plan Check / Job No.
B25LA13242
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
ePlan: New detached shed structure in the rear of lot on deep foundation. COMPLY WITH DEPARTMENT ORDER effective date 01/09/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 7/28/2025
Issuing Office
Current Status
CofO Issued on 2/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2025 APPLICANT
Assigned to Plan Check Engineer 4/10/2025 KEVIN MORALES
Corrections Issued 4/16/2025 KEVIN MORALES
Quality Review Completed 4/16/2025 EUGENE BARBEAU
Applicant returned to address corrections 4/25/2025 KEVIN MORALES
Applicant returned to address corrections 5/21/2025 KEVIN MORALES
Plan Check Approved 7/23/2025 KEVIN MORALES
Issued 7/28/2025 APPLICANT
CofO in Progress 2/2/2026 JACOB SEGURA
Permit Finaled 2/19/2026 DANIEL SANCHEZ
CofO Issued 2/19/2026 DANIEL SANCHEZ
Permit Finaled 2/19/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/26/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/26/2025 LEE GUILBEAUX
Public Works-Sewers Cleared 4/26/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/27/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 7/23/2025 KEVIN MORALES

Contact Information

Contractor Fiske Kevin Construction; Lic. No.: 841233-B       ,
Engineer Peck,, Christopher Mount; Lic. No.: NA58162       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/6/2025 Approved JACOB SEGURA
Footing/Foundation/Slab 8/11/2025 Partial Approval JACOB SEGURA
ELECTRICAL-Rough 8/15/2025 Approved FERMIN RUBIO
BUILDING-Rough-Frame 8/28/2025 Corrections Issued JACOB SEGURA
Green Building Rough 8/28/2025 Partial Approval JACOB SEGURA
Verify Sprinkler Sign Off 8/28/2025 Not Ready for Inspection JACOB SEGURA
BUILDING-Rough-Frame 10/8/2025 Partial Approval JACOB SEGURA
Final 10/8/2025 Corrections Issued JACOB SEGURA
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Partial Approval JACOB SEGURA
Insulation 10/8/2025 Partial Approval JACOB SEGURA
Interior/Exterior Lathing 10/8/2025 Partial Approval JACOB SEGURA
BUILDING-Rough-Frame 11/6/2025 Approved JACOB SEGURA
Excavation/Setback/Form/Re-Bar 11/6/2025 Approved JACOB SEGURA
Final 11/6/2025 Corrections Issued JACOB SEGURA
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Approved JACOB SEGURA
Footing/Foundation/Slab 11/6/2025 Approved JACOB SEGURA
Green Building Final 11/6/2025 Approved JACOB SEGURA
Green Building Rough 11/6/2025 Approved JACOB SEGURA
Insulation 11/6/2025 Approved JACOB SEGURA
Interior/Exterior Lathing 11/6/2025 Approved JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Not Required JACOB SEGURA
Service/Power Release 11/6/2025 Not Required JACOB SEGURA
Smoke Detectors 11/6/2025 Not Ready for Inspection JACOB SEGURA
Verify Sprinkler Sign Off 11/6/2025 Approved JACOB SEGURA
Final 12/4/2025 Corrections Issued JACOB SEGURA
Final 1/12/2026 OK to Issue CofO JACOB SEGURA
Smoke Detectors 1/12/2026 Approved JACOB SEGURA
ELECTRICAL-Final 1/23/2026 Approved JACOB SEGURA
HVAC-Final 1/23/2026 Approved JACOB SEGURA
PLUMBING-Final 1/23/2026 Approved JACOB SEGURA