713-715 W 66TH ST 90044

Certificate Information: 713-715 W 66TH ST 90044

Application / Permit
25010-10000-01401
Plan Check / Job No.
B25LA12857
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Two new two-story detached accessory dwelling units per GCS 66323(a)(4).
Permit Issued
Issued on 9/30/2025
Issuing Office
Current Status
Issued on 9/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 ALEXANDER JOO
Corrections Issued 4/19/2025 ALEXANDER JOO
Quality Review Completed 4/23/2025 GARO TELMI
Applicant returned to address corrections 8/5/2025 ALEXANDER JOO
Applicant returned to address corrections 8/29/2025 ALEXANDER JOO
Applicant returned to address corrections 9/23/2025 ALEXANDER JOO
Plan Check Approved 9/29/2025 ALEXANDER JOO
Issued 9/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/6/2025 CINDY QI
Highway dedication Cleared 5/6/2025 CINDY QI
Roof/Waste drainage to street Cleared 5/6/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 5/7/2025 CINDY QI
Sewer availability Cleared 5/7/2025 CINDY QI
Construction near power lines Cleared 5/30/2025 EDGAR PASCUA

Contact Information

Contractor Owner-Builder       ,
Engineer Herrera,, Edgar E; Lic. No.: C67603 1929 GREENLEAF DR      WEST COVINA, CA 91792

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/27/2025 Corrections Issued BARRY HACHE
Underground Mechanical 10/27/2025 Not Ready for Inspection BARRY HACHE
Excavation/Setback/Form/Re-Bar 11/4/2025 Corrections Issued BARRY HACHE
Underground Mechanical 11/4/2025 Not Ready for Inspection BARRY HACHE
Excavation/Setback/Form/Re-Bar 12/16/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 12/16/2025 Not Ready for Inspection BARRY HACHE
Underground Mechanical 12/16/2025 Not Ready for Inspection BARRY HACHE
Excavation/Setback/Form/Re-Bar 12/18/2025 Approved BARRY HACHE
PLUMBING-Rough 12/18/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 12/22/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 5/18/2026 Corrections Issued LUIS CASTRO
Verify Sprinkler Sign Off 5/18/2026 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/21/2026 Partial Approval LUIS CASTRO
Verify Sprinkler Sign Off 5/21/2026 Approved LUIS CASTRO
BUILDING-Rough-Frame 6/11/2026 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/15/2026 Partial Approval LUIS CASTRO