11963-11965 W BRAY ST 90230
Certificate Information: 11963-11965 W BRAY ST 90230
- Application / Permit
- 25010-10000-01318
- Plan Check / Job No.
- B25LA12097
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] NEW 2-STORY TWO UNIT ADU PER GC 66323(a)(4)
- Permit Issued
- Issued on 7/25/2025
- Issuing Office
- Current Status
- CofO Issued on 4/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2025 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/8/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 4/25/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/1/2025 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 6/10/2025 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 7/20/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 7/24/2025 | MAHNAZ NOURHASHEMI |
| Issued | 7/25/2025 | APPLICANT |
| CofO in Progress | 4/23/2026 | ANTHONY EGSON |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
| CofO Issued | 4/28/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 4/22/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 5/19/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/19/2025 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 5/21/2025 | SAFA JAVANMARDI |
| Specific Plan | Cleared | 6/4/2025 | EDER ROMERO |
Contact Information
| Contractor | Neo Builders And Design Inc; Lic. No.: 1114778-B | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 5306 MULHOLLAND DRIVE SUMMERVILLE, SC 29485 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 9/11/2025 | Corrections Issued | RUBEN RIVAS |
| Underground Mechanical | 9/11/2025 | Corrections Issued | RUBEN RIVAS |
| METHANE-Final | 9/17/2025 | Corrections Issued | RUBEN RIVAS |
| Excavation/Setback/Form/Re-Bar | 9/30/2025 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 9/30/2025 | Approved | RUBEN RIVAS |
| METHANE-Barrier | 9/30/2025 | Approved | RUBEN RIVAS |
| METHANE-Subgrade | 9/30/2025 | Approved | RUBEN RIVAS |
| Wood Frame | 10/15/2025 | Corrections Issued | RUBEN RIVAS |
| Deputy Wood Construction | 10/20/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 11/18/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 11/18/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 11/18/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 11/25/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 11/25/2025 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 11/25/2025 | Not Ready for Inspection | ANTHONY EGSON |
| MERV13>=Rough | 11/25/2025 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Rough | 11/25/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 11/25/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Wood Construction | 11/26/2025 | Conditional Approval | ANTHONY EGSON |
| HVAC-Rough | 11/26/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Other (see comments) | 12/1/2025 | Conditional Approval | ANTHONY EGSON |
| HVAC-Rough | 12/1/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 12/1/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/5/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 12/5/2025 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 12/5/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 12/5/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 12/16/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/16/2025 | Approved | ANTHONY EGSON |
| Insulation | 12/22/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 12/26/2025 | Approved | ANTHONY EGSON |
| Shower Pan | 12/26/2025 | Corrections Issued | ANTHONY EGSON |
| Drywall Nailing | 12/30/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/30/2025 | Approved | ANTHONY EGSON |
| Shower Pan | 12/30/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/24/2026 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Final | 3/24/2026 | Approved | ANTHONY EGSON |
| Green Building Final | 3/24/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 3/24/2026 | Approved | ANTHONY EGSON |
| METHANE-Final | 3/24/2026 | Approved | ANTHONY EGSON |
| METHANE-Rough | 3/24/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/24/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/7/2026 | Approved | ANTHONY EGSON |
| Final | 4/7/2026 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 4/7/2026 | Approved | ANTHONY EGSON |
| Smoke Detectors | 4/7/2026 | Approved | ANTHONY EGSON |
| Final | 4/15/2026 | Corrections Issued | MICHAEL ALLEN |
| Final | 4/22/2026 | OK to Issue CofO | ANTHONY EGSON |