11963-11965 W BRAY ST 90230

Certificate Information: 11963-11965 W BRAY ST 90230

Application / Permit
25010-10000-01318
Plan Check / Job No.
B25LA12097
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] NEW 2-STORY TWO UNIT ADU PER GC 66323(a)(4)
Permit Issued
Issued on 7/25/2025
Issuing Office
Current Status
CofO Issued on 4/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2025 APPLICANT
Assigned to Plan Check Engineer 4/3/2025 MAHNAZ NOURHASHEMI
Corrections Issued 4/8/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 4/25/2025 HERNAN ARREOLA
Applicant returned to address corrections 6/1/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 6/10/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 7/20/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 7/24/2025 MAHNAZ NOURHASHEMI
Issued 7/25/2025 APPLICANT
CofO in Progress 4/23/2026 ANTHONY EGSON
Permit Finaled 4/28/2026 RICHARD STEINBACH
CofO Issued 4/28/2026 RICHARD STEINBACH
Permit Finaled 4/28/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/22/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/22/2025 SAFA JAVANMARDI
Sewer availability Cleared 4/22/2025 SAFA JAVANMARDI
Construction near power lines Cleared 5/19/2025 RIDWAN HARDY
Construction within easement Cleared 5/19/2025 RIDWAN HARDY
Roof/Waste drainage to street Cleared 5/21/2025 SAFA JAVANMARDI
Specific Plan Cleared 6/4/2025 EDER ROMERO

Contact Information

Contractor Neo Builders And Design Inc; Lic. No.: 1114778-B       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 5306 MULHOLLAND DRIVE      SUMMERVILLE, SC 29485

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 9/11/2025 Corrections Issued RUBEN RIVAS
Underground Mechanical 9/11/2025 Corrections Issued RUBEN RIVAS
METHANE-Final 9/17/2025 Corrections Issued RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 9/30/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 9/30/2025 Approved RUBEN RIVAS
METHANE-Barrier 9/30/2025 Approved RUBEN RIVAS
METHANE-Subgrade 9/30/2025 Approved RUBEN RIVAS
Wood Frame 10/15/2025 Corrections Issued RUBEN RIVAS
Deputy Wood Construction 10/20/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 11/18/2025 Approved RUBEN RIVAS
HVAC-Rough 11/18/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 11/18/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 11/25/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 11/25/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 11/25/2025 Not Ready for Inspection ANTHONY EGSON
MERV13>=Rough 11/25/2025 Not Ready for Inspection ANTHONY EGSON
METHANE-Rough 11/25/2025 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 11/25/2025 Not Ready for Inspection ANTHONY EGSON
Deputy Wood Construction 11/26/2025 Conditional Approval ANTHONY EGSON
HVAC-Rough 11/26/2025 Not Ready for Inspection ANTHONY EGSON
Deputy Other (see comments) 12/1/2025 Conditional Approval ANTHONY EGSON
HVAC-Rough 12/1/2025 Not Ready for Inspection ANTHONY EGSON
Wood Frame 12/1/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 12/5/2025 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Partial Approval ANTHONY EGSON
Green Building Rough 12/5/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 12/5/2025 Not Ready for Inspection ANTHONY EGSON
Wood Frame 12/5/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 12/16/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/16/2025 Approved ANTHONY EGSON
Insulation 12/22/2025 Corrections Issued ANTHONY EGSON
Insulation 12/26/2025 Approved ANTHONY EGSON
Shower Pan 12/26/2025 Corrections Issued ANTHONY EGSON
Drywall Nailing 12/30/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/30/2025 Approved ANTHONY EGSON
Shower Pan 12/30/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 3/24/2026 Partial Approval ANTHONY EGSON
ELECTRICAL-Final 3/24/2026 Approved ANTHONY EGSON
Green Building Final 3/24/2026 Approved ANTHONY EGSON
HVAC-Final 3/24/2026 Approved ANTHONY EGSON
METHANE-Final 3/24/2026 Approved ANTHONY EGSON
METHANE-Rough 3/24/2026 Approved ANTHONY EGSON
PLUMBING-Final 3/24/2026 Approved ANTHONY EGSON
BUILDING-Rough-Frame 4/7/2026 Approved ANTHONY EGSON
Final 4/7/2026 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV Approved ANTHONY EGSON
Service/Power Release 4/7/2026 Approved ANTHONY EGSON
Smoke Detectors 4/7/2026 Approved ANTHONY EGSON
Final 4/15/2026 Corrections Issued MICHAEL ALLEN
Final 4/22/2026 OK to Issue CofO ANTHONY EGSON