8033 S EL MANOR AVE 90045
Certificate Information: 8033 S EL MANOR AVE 90045
- Application / Permit
- 25010-10000-01313
- Plan Check / Job No.
- B25LA12071
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- EPLAN: NEW 16'-0" X 12'-6" DETACHED PATIO COVER, ALL WORK PER ENG.
- Permit Issued
- Issued on 5/16/2025
- Issuing Office
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/2/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/15/2025 | LUISANGEL VALENZUELA |
| Issued | 5/16/2025 | APPLICANT |
| Permit Finaled | 12/12/2025 | RICHARD STEINBACH |
| CofO Issued | 12/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/21/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2025 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 5/13/2025 | TINA MIRANDA |
Contact Information
| Architect | Samson,, Charles Andrew H; Lic. No.: C22979 | 6119 MARY ELLEN AVENUE VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/10/2025 | No Access for Inspection | RUBEN RIVAS |
| Footing/Foundation/Slab | 6/10/2025 | No Access for Inspection | RUBEN RIVAS |
| METHANE-Barrier | 6/10/2025 | Not Ready for Inspection | RUBEN RIVAS |
| METHANE-Subgrade | 6/10/2025 | No Access for Inspection | RUBEN RIVAS |
| Excavation/Setback/Form/Re-Bar | 6/11/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Approved | RUBEN RIVAS |
| Verify Sprinkler Sign Off | 6/27/2025 | Partial Approval | RUBEN RIVAS |
| Wood Frame | 6/27/2025 | Partial Approval | RUBEN RIVAS |
| Verify Sprinkler Sign Off | 8/21/2025 | Approved | RUBEN RIVAS |
| Wood Frame | 8/21/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 8/29/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 9/10/2025 | Approved | RUBEN RIVAS |
| Final | 12/2/2025 | Partial Approval | RUBEN RIVAS |
| Footing/Foundation/Slab | 12/2/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 12/2/2025 | Approved | RUBEN RIVAS |