608 N VIA DE LA PAZ 90272

Certificate Information: 608 N VIA DE LA PAZ 90272

Application / Permit
25010-10000-01311
Plan Check / Job No.
B25LA10917
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**2025 WILDFIRE ELIGIBLE PROJECT PER EO1**EPLAN* NEW 1-STORY ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). CONSTRUCTED IN SAME LOCATION AND TO THE SAME DIMENSION AS (E) DETACHED GARAGE. wildfire rebuild NFPA 13D. SOLAR INSTALLATION EXEMPT PER GOVERNOR'S ORDER N-29-25.
Permit Issued
Issued on 12/15/2025
Issuing Office
Current Status
Issued on 12/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/20/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 VIVIAN LAO
Corrections Issued 3/27/2025 VIVIAN LAO
Quality Review Completed 3/27/2025 JOHN FRANCIA
Applicant returned to address corrections 4/30/2025 VIVIAN LAO
Applicant returned to address corrections 5/1/2025 VIVIAN LAO
Applicant returned to address corrections 5/16/2025 VIVIAN LAO
Applicant returned to address corrections 5/28/2025 VIVIAN LAO
Plan Check Approved 7/11/2025 VIVIAN LAO
No Progress 9/19/2025 VIVIAN LAO
Plan Check Approved 12/9/2025 VIVIAN LAO
Issued 12/15/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/3/2025 VISHAL MANDALIA
Sewer availability Cleared 4/3/2025 VISHAL MANDALIA
Hydrant and Access approval Cleared 4/11/2025 JERRY KAO
Eng Process Fee Ord 176,300 Cleared 4/15/2025 VISHAL MANDALIA
Roof/Waste drainage to street Cleared 4/15/2025 VISHAL MANDALIA
Construction within easement Cleared 5/14/2025 RIDWAN HARDY

Contact Information

Architect Liu-Hogan,, Nuo; Lic. No.: C37147 3127 S BEVERLY DRIVE      LOS ANGELES, CA 90034
Contractor Hogan Construction And Development Inc; Lic. No.: 1085371-B       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/11/2026 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 2/11/2026 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 3/5/2026 Approved MICHAEL ALLEN
Footing/Foundation/Slab 3/5/2026 Approved MICHAEL ALLEN
ELECTRICAL-Rough 5/28/2026 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 5/28/2026 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 6/9/2026 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 6/11/2026 Conditional Approval STEPHANIE SWANSON
PLUMBING-Rough 7/2/2026 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 7/6/2026 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 7/7/2026 Approved MICHAEL ALLEN
HVAC-Rough 7/20/2026 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 7/23/2026 Approved EVAN COOPER