1839 S HOOVER ST 90006
Certificate Information: 1839 S HOOVER ST 90006
- Application / Permit
- 25010-10000-01310
- Plan Check / Job No.
- B25LA11995
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Canopy
- Work Description
- New fabric canopy on day care school playground. Accessory use to the adjacent existing day care building.
- Permit Issued
- Issued on 12/8/2025
- Issuing Office
- Metro
- Current Status
- Issued on 12/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | HELEN NGUYEN |
| Corrections Issued | 4/2/2025 | HELEN NGUYEN |
| Assigned to Zoning Architect | 4/3/2025 | AMIR NAKHLA |
| Quality Review Completed | 6/10/2025 | PETER KIM |
| Disabled Access Plans Picked Up | 6/10/2025 | APPLICANT |
| Applicant returned to address corrections | 9/11/2025 | HELEN NGUYEN |
| Plan Check Approved | 9/24/2025 | HELEN NGUYEN |
| Issued | 12/8/2025 | APPLICANT |
Permit Application Clearance Information
| Zoning Plan Check | Cleared | 4/16/2025 | HELEN NGUYEN |
| City owned building/parcel | Cleared | 6/30/2025 | MASON NG |
| Roof/Waste drainage to street | Cleared | 7/8/2025 | CELINA MORENO |
| Sewer availability | Cleared | 7/8/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2025 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 7/21/2025 | KURT CORRAL |
| Fire Marshal Fire Life Safety | Cleared | 8/28/2025 | SARAH ZHANG |
| DAS Clearance | Cleared | 9/23/2025 | HELEN NGUYEN |
Contact Information
| Contractor | Teo'S Construction; Lic. No.: 778080-B | 1267 E 53RD STREET LOS ANGELES, CA 90011 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Engineer | Lipa,, Mateusz; Lic. No.: S6971 | 864 DOWNING CIRCLE LINCOLN, CA 95648 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/9/2026 | Not Ready for Inspection | LARRY ARNICK |
| Piling/Pier/Caisson | 1/9/2026 | Approved | LARRY ARNICK |