3130 1/2 E ARVIA ST 90065
Certificate Information: 3130 1/2 E ARVIA ST 90065
- Application / Permit
- 25010-10000-01268
- Plan Check / Job No.
- B25LA11497
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONSTRUCTION OF DETACHED ACCESSORY DWELLING UNIT GC 66323(a)(2)
- Permit Issued
- Issued on 7/25/2025
- Issuing Office
- Current Status
- CofO Issued on 1/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2025 | SHANGQIN XIE |
| Corrections Issued | 4/28/2025 | SHANGQIN XIE |
| Applicant returned to address corrections | 5/7/2025 | SHANGQIN XIE |
| Applicant returned to address corrections | 6/3/2025 | SHANGQIN XIE |
| Plan Check Approved | 7/23/2025 | SHANGQIN XIE |
| Issued | 7/25/2025 | APPLICANT |
| CofO in Progress | 1/14/2026 | ALIZAH MAYAGOITIA |
| Permit Finaled | 1/14/2026 | DEROLD HAUFF |
| CofO Issued | 1/14/2026 | DEROLD HAUFF |
| Permit Finaled | 1/14/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Supp. Use District POD/CDO/TDO | Cleared | 5/6/2025 | ANDREA MAGANA-WITHERS |
| Address approval | Cleared | 5/8/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 5/8/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 5/8/2025 | DERRICK MAGEE |
| GPI Written Notices | Cleared | 6/3/2025 | SHANGQIN XIE |
| Grading Pre-Inspection | Cleared | 6/3/2025 | SHANGQIN XIE |
| Construction near power lines | Cleared | 7/21/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Bridgeline Construction; Lic. No.: 1078101-B | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/7/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/11/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/13/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/14/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/14/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 8/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 8/15/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/2/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Partial Approval | GEM DE OCAMPO |
| PLUMBING-Rough | 9/4/2025 | Partial Approval | GEM DE OCAMPO |
| Sewer | 9/4/2025 | Not Ready for Inspection | GEM DE OCAMPO |
| Sewer | 9/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 9/16/2025 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/17/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/22/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/30/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/30/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 11/7/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 11/7/2025 | Corrections Issued | GEM DE OCAMPO |
| Deputy Drilled-In Anchors | 11/12/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 11/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/24/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/24/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 12/30/2025 | Not Ready for Inspection | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | RONNIE MEDINA |
| Service/Power Release | 12/30/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Smoke Detectors | 12/30/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Final | 1/8/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 1/8/2026 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 1/8/2026 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/13/2026 | OK to Issue CofO | ALIZAH MAYAGOITIA |