618-618 1/2 N IMOGEN AVE 90026
Certificate Information: 618-618 1/2 N IMOGEN AVE 90026
- Application / Permit
- 25010-10000-01260
- Plan Check / Job No.
- B25LA11349
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 1) PROPOSED 3-STORY DUPLEX W/ ATTACHED GARAGE (FRONT)
- Permit Issued
- Issued on 11/20/2025
- Issuing Office
- Current Status
- Issued on 11/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | VARAND SARKISIAN |
| Assigned to Zoning Architect | 3/27/2025 | NICOLE SALEEBA |
| Corrections Issued | 4/1/2025 | VARAND SARKISIAN |
| Quality Review Completed | 4/14/2025 | GARO TELMI |
| Applicant returned to address corrections | 10/1/2025 | VARAND SARKISIAN |
| Plan Check Approved | 10/21/2025 | VARAND SARKISIAN |
| Issued | 11/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2025 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 4/7/2025 | JEREMY CHOK |
| Hydrant and Access approval | Cleared | 4/18/2025 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 5/29/2025 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/29/2025 | JEREMY CHOK |
| Frnt yard landscape/Water mgmt | Cleared | 7/16/2025 | DAVID URITA |
| Landscape for retaining wall | Cleared | 7/16/2025 | DAVID URITA |
| Zoning Plan Check | Cleared | 9/9/2025 | NICOLE SALEEBA |
| Grading Pre-Inspection | Cleared | 10/21/2025 | VARAND SARKISIAN |
Contact Information
| Contractor | Riviera Building & Design Inc; Lic. No.: 878203-B | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/21/2026 | Corrections Issued | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/28/2026 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 1/28/2026 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 2/2/2026 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 2/2/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 2/9/2026 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/9/2026 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 2/12/2026 | Corrections Issued | FREDDIE RIVERA |
| Pre-Inspection | 2/12/2026 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/24/2026 | Approved | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 2/25/2026 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2026 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2026 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 4/23/2026 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 4/30/2026 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/11/2026 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/11/2026 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/11/2026 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 5/11/2026 | Approved | FREDDIE RIVERA |
| Wood Frame | 5/11/2026 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 5/18/2026 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/22/2026 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 5/22/2026 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/3/2026 | Approved | GEM DE OCAMPO |
| Sewer | 7/15/2026 | Approved | FREDDIE RIVERA |