1132 1/4-3/4 E ADAMS BLVD 90011
Certificate Information: 1132 1/4-3/4 E ADAMS BLVD 90011
- Application / Permit
- 25010-10000-01253
- Plan Check / Job No.
- B25LA11269
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) TWO STORY DUPLEX (SFD AT FIRST LEVEL AND ADU AT UPPER LEVEL PER LAMC 12.22 A.33(b)(1). NFPA 13R FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 3/6/2026
- Issuing Office
- Metro
- Current Status
- Issued on 3/6/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/24/2025 | APPLICANT |
| Assigned to Zoning Architect | 3/27/2025 | MEGAN KOLP |
| Assigned to Plan Check Engineer | 4/3/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 4/14/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 4/23/2025 | KEN GILL |
| Building Plans Picked Up | 4/30/2025 | APPLICANT |
| Plan Check Approved | 1/23/2026 | SERGIO GUTIERREZ |
| Issued | 3/6/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/25/2025 | TREVOR QUAN |
| Community Plan Implem. Overlay | Cleared | 5/25/2025 | TREVOR QUAN |
| Permit | Cleared | 5/25/2025 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 5/25/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 6/3/2025 | TREVOR QUAN |
| "D" conditions | Cleared | 8/5/2025 | JAZMIN ROQUE |
| Community Plan Implem. Overlay | Cleared | 8/15/2025 | MIGUEL ORNELAS |
| Trees in Parkway | Cleared | 8/15/2025 | MIGUEL ORNELAS |
| Community Plan Implem. Overlay | Cleared | 9/10/2025 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/16/2025 | KURT CORRAL |
| Community Plan Implem. Overlay | Cleared | 10/17/2025 | JOSE CARDENAS |
| Community Plan Implem. Overlay | Cleared | 12/11/2025 | DAISY BENICIA |
| Zoning Plan Check | Cleared | 1/9/2026 | MEGAN KOLP |
Contact Information
| Contractor | E3 Contractors Llc; Lic. No.: 1131488-B | 12015 SLAUSON AVE STE F SANTA FE SPRINGS, CA 90670 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| HVAC-Rough | 7/22/2026 |
| Wood Frame | 7/22/2026 |
Inspection Request History
| PLUMBING-Rough | 4/8/2026 | Approved | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 4/10/2026 | Corrections Issued | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/11/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 5/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 6/8/2026 | Conditional Approval | ALEX COLIN |
| HVAC-Rough | 6/23/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/23/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/2/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/6/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/6/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/13/2026 | No Access for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 7/15/2026 | No Access for Inspection | BARRY HACHE |
| PLUMBING-Rough | 7/15/2026 | No Access for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 7/16/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 7/16/2026 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 7/17/2026 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 7/17/2026 | Approved | FREDDIE RIVERA |