1141 N BANNING BLVD 90744

Certificate Information: 1141 N BANNING BLVD 90744

Application / Permit
25010-10000-01248
Plan Check / Job No.
B25LA08049
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ALL ELECTRIC 1-STORY ACCESSORY DWELLING UNIT WITH ATTACHED STORAGE (EXTERIOR ACCESS ONLY) PER GC 66323(a)(1). NFPA-13D FIRE SPRINKLERS TO BE INSTALLED.
Permit Issued
Issued on 3/3/2026
Issuing Office
Current Status
Issued on 3/3/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/4/2025 APPLICANT
Assigned to Zoning Architect 3/6/2025 KAITA SAITO
Assigned to Plan Check Engineer 3/20/2025 MADISON ODELL
Corrections Issued 3/24/2025 JAD BASMA
Quality Review Completed 3/26/2025 PRANITA SHAH
Applicant returned to address corrections 11/18/2025 MADISON ODELL
Applicant returned to address corrections 12/9/2025 MADISON ODELL
Plan Check Approved 12/17/2025 MADISON O'DELL
Issued 3/3/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/27/2025 MICHAEL BROWN
Permit Cleared 10/27/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 10/27/2025 MICHAEL BROWN
Zoning Plan Check Cleared 11/18/2025 KAITA SAITO
Eng Process Fee Ord 176,300 Cleared 12/9/2025 MICHAEL BROWN
Sewer availability Cleared 12/9/2025 MICHAEL BROWN
Abandoned oil well Cleared 12/12/2025 GILBERT URREA
Abandoned oil well Cleared 12/12/2025 GILBERT URREA
Hydrant and Access approval Cleared 12/12/2025 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/5/2026 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 3/5/2026 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 3/5/2026 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 3/5/2026 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 3/10/2026 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 3/10/2026 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 3/11/2026 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/31/2026 Partial Approval JOSEPH MCGARRY
Gas Test 3/31/2026 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 3/31/2026 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Partial Approval EUGENE CASSIDY