4112 N WOODCLIFF ROAD 91403

Certificate Information: 4112 N WOODCLIFF ROAD 91403

Application / Permit
25010-10000-01231
Plan Check / Job No.
B25LA11130
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
-PROPOSED 2 STORY SINGLE FAMILY HOME WITH ATTACHED TWO CAR GARAGE.
Permit Issued
Issued on 7/30/2025
Issuing Office
Current Status
Issued on 7/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 VARAND SARKISIAN
Assigned to Zoning Architect 3/27/2025 NICOLE SALEEBA
Corrections Issued 4/1/2025 VARAND SARKISIAN
Quality Review Completed 4/9/2025 GARO TELMI
Applicant returned to address corrections 6/17/2025 VARAND SARKISIAN
Plan Check Approved 7/17/2025 VARAND SARKISIAN
Issued 7/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/10/2025 JESUS LUNA
BHO/Hillside ordinance Cleared 4/10/2025 JESUS LUNA
BHO/Hillside ordinance Cleared 4/10/2025 JESUS LUNA
BHO/Hillside ordinance Cleared 4/10/2025 JESUS LUNA
BHO/Hillside ordinance Cleared 4/10/2025 JESUS LUNA
BHO/Hillside ordinance Cleared 4/10/2025 JESUS LUNA
Hydrant and Access approval Cleared 4/10/2025 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 4/11/2025 JESUS LUNA
Sewer availability Cleared 4/11/2025 JESUS LUNA
CPC Cleared 5/22/2025 DAVID URITA
Roof/Waste drainage to street Cleared 6/18/2025 SAFA JAVANMARDI
Zoning Plan Check Cleared 6/27/2025 NICOLE SALEEBA
Grading Pre-Inspection Cleared 7/17/2025 VARAND SARKISIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/2/2025 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/23/2025 Approved JACK KARGODORIAN
Sewer 10/29/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/25/2025 Partial Approval WILLIAM WREN
Deputy Reinf. Concrete 12/10/2025 Conditional Approval JOAQUIN GREENOUGH
Deputy Reinf. Concrete 12/12/2025 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 12/18/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 1/14/2026 Approved JACK KARGODORIAN
HVAC-Rough 1/15/2026 Approved JACK KARGODORIAN
ELECTRICAL-Rough 1/29/2026 Approved JACK KARGODORIAN
Wood Frame 1/29/2026 Partial Approval JACK KARGODORIAN
Shower Pan 2/2/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/6/2026 Partial Approval JACK KARGODORIAN
Deputy Steel/Welding 2/17/2026 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 2/26/2026 Approved JACK KARGODORIAN
Green Building Rough 2/26/2026 Approved JACK KARGODORIAN
Insulation 2/26/2026 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 2/26/2026 Approved JACK KARGODORIAN
Interior/Exterior Lathing 3/3/2026 Approved MICHAEL CORTEZ
Drywall Nailing 3/11/2026 Approved MICHAEL CORTEZ
Underground Mechanical 5/4/2026 Partial Approval MICHAEL CORTEZ
Underground Mechanical 5/20/2026 Partial Approval MISAEL ESPARZA
ELECTRICAL-Final 6/24/2026 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Final 7/2/2026 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/13/2026 Approved DAVID ANDERSON