3503 N ALGINET DR 91436
Certificate Information: 3503 N ALGINET DR 91436
- Application / Permit
- 25010-10000-01224
- Plan Check / Job No.
- B25LA11093
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] NEW 1-STORY ADU PER GC 66323(a)(2)
- Permit Issued
- Issued on 6/30/2025
- Issuing Office
- Current Status
- Issued on 6/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/3/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 4/23/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/1/2025 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 6/13/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 6/30/2025 | MAHNAZ NOURHASHEMI |
| Issued | 6/30/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/16/2025 | BIAINA HARITUNIAN |
| Specific Plan | Cleared | 5/5/2025 | JUDE HERNANDEZ |
| GPI Written Notices | Cleared | 6/1/2025 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 6/1/2025 | MAHNAZ NOURHASHEMI |
| Roof/Waste drainage to street | Cleared | 6/3/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
| Engineer | Mohammadi,, Saeid; Lic. No.: NA82330 | , |
| Engineer | Noorzay,, Maihan; Lic. No.: GE3085 | 16531 ORANGEHAVEN LANE RIVERSIDE, CA 92503 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| BUILDING-Rough-Frame | 6/12/2026 Time Frame: 11-1 |
| Verify Sprinkler Sign Off | 6/12/2026 Time Frame: 11-1 |
| Green Building Rough | 6/12/2026 Time Frame: 11-1 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/4/2025 | Conditional Approval | JOHN KIDWELL |
| Pre-Inspection | 8/4/2025 | Partial Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/4/2025 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/10/2025 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/15/2025 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 9/24/2025 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/26/2025 | Corrections Issued | SEAN WIRCH |
| Footing/Foundation/Slab | 9/26/2025 | Partial Approval | SEAN WIRCH |
| Reinforced Concrete Frame | 11/13/2025 | Partial Approval | MORRIS JACKSON |
| Wood Frame | 3/13/2026 | Partial Approval | THOMAS FINNILA |