2677 S FEDERAL AVE 90064

Certificate Information: 2677 S FEDERAL AVE 90064

Application / Permit
25010-10000-01202
Plan Check / Job No.
B25LA10899
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan New detached 31' 9 1/2" x 31' 9 1/2" ADU per LAMC LAMC 12.22 A.33(b)(1)3. All work per engineering.
Permit Issued
Issued on 5/30/2025
Issuing Office
Current Status
CofO Issued on 4/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2025 APPLICANT
Assigned to Plan Check Engineer 3/25/2025 NAREG ATARIAN
Corrections Issued 3/25/2025 NAREG ATARIAN
Applicant returned to address corrections 5/20/2025 NAREG ATARIAN
Applicant returned to address corrections 5/22/2025 LUISANGEL VALENZUELA
Plan Check Approved 5/28/2025 NAREG ATARIAN
Issued 5/30/2025 APPLICANT
CofO in Progress 2/10/2026 ARAM AVEDISIAN
CofO in Progress 2/24/2026 ANDREW NAVE
Permit Finaled 4/3/2026 RICHARD STEINBACH
CofO Issued 4/3/2026 RICHARD STEINBACH
Permit Finaled 4/3/2026 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 4/11/2025 ENRIQUE ACOSTA
Address approval Cleared 4/23/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 5/12/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 5/14/2025 XOCHITL ARQUIETA
Sewer availability Cleared 5/14/2025 XOCHITL ARQUIETA
Specific Plan Cleared 5/20/2025 EDER ROMERO

Contact Information

Architect Howell,, Ronald Edwards; Lic. No.: C21122 P O BOX 661007      LOS ANGELES, CA 90066
Architect Howell,, Ronald Edwards; Lic. No.: NA21122       ,
Contractor A B Construction; Lic. No.: 936625-B       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/3/2025 Approved WILBER ROSALES
Footing/Foundation/Slab 6/3/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 6/12/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Partial Approval WILBER ROSALES
PLUMBING-Rough 6/24/2025 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 7/10/2025 Approved WILBER ROSALES
HVAC-Rough 7/10/2025 Corrections Issued WILBER ROSALES
Underground Mechanical 7/10/2025 Partial Approval WILBER ROSALES
BUILDING-Rough-Frame 7/17/2025 Not Ready for Inspection WILBER ROSALES
Green Building Rough 7/17/2025 Not Ready for Inspection WILBER ROSALES
PLUMBING-Rough 7/17/2025 Not Ready for Inspection WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Approved BOBBY KEY
HVAC-Rough 7/21/2025 Approved BOBBY KEY
PLUMBING-Rough 7/21/2025 Approved BOBBY KEY
Sewer 7/25/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 9/16/2025 Approved KIRK SANDERS
ELECTRICAL-Final 9/16/2025 Corrections Issued KIRK SANDERS
Green Building Rough 9/16/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 9/16/2025 Partial Approval KIRK SANDERS
Insulation 9/23/2025 Corrections Issued CARLOS MATAMOROS
Insulation 9/25/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 9/25/2025 Corrections Issued KIRK SANDERS
Special/Order Compliance 9/25/2025 Not Ready for Inspection CARLOS MATAMOROS
Drywall Nailing 10/1/2025 Approved ARAM AVEDISIAN
Insulation 10/1/2025 Approved ARAM AVEDISIAN
Shower Pan 11/14/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 11/24/2025 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 11/26/2025 Approved KIRK SANDERS
ELECTRICAL-Final 12/11/2025 Corrections Issued KIRK SANDERS
Final 12/11/2025 Corrections Issued KIRK SANDERS
Green Building Final 12/11/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Final 12/11/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 12/11/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Not Required KIRK SANDERS
Service/Power Release 12/11/2025 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 12/11/2025 Approved KIRK SANDERS
Final 2/9/2026 Conditional Approval ARAM AVEDISIAN
Green Building Final 2/9/2026 Approved ARAM AVEDISIAN
Service/Power Release 2/9/2026 Not Required ARAM AVEDISIAN
Final 2/24/2026 Corrections Issued ARAM AVEDISIAN