9600 S SEPULVEDA BLVD 90045
Certificate Information: 9600 S SEPULVEDA BLVD 90045
- Application / Permit
- 25010-10000-01170
- Plan Check / Job No.
- B25LA10524
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- LAX-ATMP *ePlan**LAX** LAWA ATMP Roadway Project - New Pedestrian Bridge over 96th St.
- Permit Issued
- Issued on 4/3/2026
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2025 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/27/2025 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 4/1/2025 | LIPING TENG |
| Applicant returned to address corrections | 5/28/2025 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 6/3/2025 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/13/2025 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/17/2025 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 3/26/2026 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 3/27/2026 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/31/2026 | FARSHAD ALIMOHAMADI |
| Issued | 4/3/2026 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/28/2025 | JASON CHAN |
| Miscellaneous | Cleared | 5/28/2025 | JASON CHAN |
| Miscellaneous | Cleared | 5/28/2025 | JASON CHAN |
| Miscellaneous | Cleared | 5/28/2025 | JASON CHAN |
| ZA Case | Cleared | 5/28/2025 | JASON CHAN |
| ZA Case | Cleared | 5/28/2025 | JASON CHAN |
| ZA Case | Cleared | 5/28/2025 | JASON CHAN |
| ZA Case | Cleared | 5/28/2025 | JASON CHAN |
| Project Permit | Cleared | 6/2/2025 | CHRISTOPHER MARTINEZ |
| Hydrant and Access approval | Cleared | 6/4/2025 | JOHN CONNEALLY |
| Address approval | Cleared | 6/25/2025 | MAHELET GEBEYHU |
| Encroachment in public way | Cleared | 6/25/2025 | MAHELET GEBEYHU |
| Highway dedication | Cleared | 6/25/2025 | MAHELET GEBEYHU |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2025 | MAHELET GEBEYHU |
| Community Plan Implem. Overlay | Cleared | 7/1/2025 | CAELAN RAFFERTY |
| Green Code | Cleared | 7/2/2025 | FARSHAD ALIMOHAMADI |
| Specific Plan | Cleared | 8/11/2025 | PEDRO AYALA |
| DAS Clearance | Cleared | 9/19/2025 | FARSHAD ALIMOHAMADI |
| City owned building/parcel | Cleared | 10/8/2025 | MASON NG |
| Low Impact Development (LID) | Cleared | 2/11/2026 | AMMAR ELTAWIL |
| Building over 36-ft | Cleared | 3/2/2026 | CALOSHA APPROVED |
| Roof/Waste drainage to street | Cleared | 3/13/2026 | MAHELET GEBEYHU |
Contact Information
| Contractor | Skanska Usa Civil West California District Inc; Lic. No.: 140069-A | 1995 AGUA MANSA RD RIVERSIDE, CA 92509 |
| Engineer | Zhang,, Xu; Lic. No.: S6936 | 1007 N SEPULVEDA BLVD 968 MANHATTAN BEACH, CA 90267 |
Inspector Information
| NICK LAROCCA, (213) 473-2153 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/25/2026 | Partial Approval | NICK LAROCCA |
| Deputy Grading | 6/26/2026 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 6/26/2026 | Approved | NICK LAROCCA |
| Piling/Pier/Caisson | 6/26/2026 | Partial Inspection | NICK LAROCCA |
| Deputy Grading | 6/29/2026 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 6/29/2026 | Approved | NICK LAROCCA |
| Deputy Grading | 7/2/2026 | Conditional Approval | DANIEL ARMENTA |
| Deputy Reinf. Concrete | 7/2/2026 | Conditional Approval | DANIEL ARMENTA |
| Deputy Grading | 7/7/2026 | Conditional Approval | DAVID TSAU |
| Deputy Reinf. Concrete | 7/7/2026 | Conditional Approval | DAVID TSAU |
| Deputy Grading | 7/8/2026 | Conditional Approval | DAVID TSAU |
| Deputy Reinf. Concrete | 7/8/2026 | Conditional Approval | DAVID TSAU |
| Pre-Inspection | 7/8/2026 | Pending Review | |
| Excavation/Setback/Form/Re-Bar | 7/18/2026 | Pending Review |