6008 S 2ND AVE 90043
Certificate Information: 6008 S 2ND AVE 90043
- Application / Permit
- 25010-10000-01153
- Plan Check / Job No.
- B25LA10376
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER LAMC 12.22 A.33(b)(1), ALL WORK PER WFPP
- Permit Issued
- Issued on 4/1/2025
- Issuing Office
- Current Status
- CofO Issued on 8/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2025 | MINA HABILI |
| Corrections Issued | 3/23/2025 | MINA HABILI |
| Building Plans Picked Up | 3/26/2025 | APPLICANT |
| Plan Check Approved | 3/28/2025 | SUNMIN LEE |
| Plan Check Approved | 3/28/2025 | NGHI SU |
| Issued | 4/1/2025 | APPLICANT |
| CofO in Progress | 8/5/2025 | MICHAEL LEWIS |
| Permit Finaled | 8/7/2025 | DEROLD HAUFF |
| CofO Issued | 8/7/2025 | DEROLD HAUFF |
| Permit Finaled | 8/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/24/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2025 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/24/2025 | JEANIE LAM |
| Sewer availability | Cleared | 3/24/2025 | JEANIE LAM |
Contact Information
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Partial Approval | SABAS ALONSO |
| Sewer | 5/6/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/6/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/14/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 5/28/2025 | Corrections Issued | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 5/28/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Rough | 5/28/2025 | Corrections Issued | WAYNE REGESTER |
| BUILDING-Rough-Frame | 5/30/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 5/30/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 5/30/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 5/30/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 5/30/2025 | Approved | WAYNE REGESTER |
| Verify Sprinkler Sign Off | 5/30/2025 | Approved | WAYNE REGESTER |
| Insulation | 6/9/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 6/9/2025 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 6/13/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 6/13/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 7/24/2025 | Approved | WAYNE REGESTER |
| Final | 7/24/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 7/24/2025 | Corrections Issued | WAYNE REGESTER |
| HVAC-Final | 7/24/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 7/24/2025 | Corrections Issued | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 7/24/2025 | SGSOV Not Required | WAYNE REGESTER |
| Service/Power Release | 7/24/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 7/24/2025 | Approved | WAYNE REGESTER |
| Final | 7/28/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 7/28/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 8/1/2025 | Partial Approval | WAYNE REGESTER |
| Green Building Final | 8/1/2025 | Approved | WAYNE REGESTER |
| Final | 8/5/2025 | OK to Issue CofO | WAYNE REGESTER |