16660 W ADDISON ST 91436
Certificate Information: 16660 W ADDISON ST 91436
- Application / Permit
- 25010-10000-01127
- Plan Check / Job No.
- B25LA06399
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- detached ADU
- Permit Issued
- Issued on 8/1/2025
- Issuing Office
- Current Status
- Issued on 8/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | ARSALAN SHABESTARI |
| Assigned to Zoning Architect | 3/6/2025 | MEGAN KOLP |
| Corrections Issued | 3/11/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 3/18/2025 | PRANITA SHAH |
| Plan Check Approved | 7/16/2025 | ARSALAN SHABESTARI |
| Issued | 8/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 3/28/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 4/3/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 6/5/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 6/5/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/29/2025 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 9/29/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 10/1/2025 | Conditional Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 10/6/2025 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/8/2025 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 12/10/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2025 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 12/15/2025 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 12/31/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 12/31/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 12/31/2025 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | THOMAS FINNILA |
| Green Building Rough | 1/20/2026 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 1/20/2026 | Approved | THOMAS FINNILA |
| Insulation | 1/28/2026 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/28/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Drywall Nailing | 2/6/2026 | Approved | THOMAS FINNILA |
| Gas Test | 4/22/2026 | Partial Approval | THOMAS FINNILA |