2438 N HARWOOD ST 90031
Certificate Information: 2438 N HARWOOD ST 90031
- Application / Permit
- 25010-10000-01089
- Plan Check / Job No.
- B25LA09731
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan DETACHED ADU PER STATE LAW CA GC 66323(a)(2) AND LAMC 2.22 A.33(c)(d) AND (g)
- Permit Issued
- Issued on 6/26/2025
- Issuing Office
- Current Status
- CofO Issued on 3/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2025 | LUKE GONZALES |
| Corrections Issued | 3/18/2025 | LUKE GONZALES |
| Applicant returned to address corrections | 4/24/2025 | KELVIN CHUONG |
| Plan Check Approved | 4/30/2025 | LUKE GONZALES |
| Issued | 6/26/2025 | APPLICANT |
| CofO in Progress | 3/24/2026 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/25/2026 | DEROLD HAUFF |
| CofO Issued | 3/25/2026 | DEROLD HAUFF |
| Permit Finaled | 3/25/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 3/24/2025 | SANDRA SOH |
| Address approval | Cleared | 3/25/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/25/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/25/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/25/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/25/2025 | LEE GUILBEAUX |
| ZI | Cleared | 4/14/2025 | YINGSHI HUANG |
Contact Information
| Contractor | Smart Eye Construction Corp; Lic. No.: 1077004-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/7/2025 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 7/11/2025 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/11/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/12/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 9/12/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 9/26/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/26/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/26/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/7/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 10/20/2025 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/20/2025 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 10/21/2025 | Conditional Approval | GEM DE OCAMPO |
| Insulation | 10/24/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 10/24/2025 | Partial Approval | DEVON JACKSON |
| Drywall Nailing | 10/29/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/29/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/31/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 3/17/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 3/17/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 3/17/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/17/2026 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 3/17/2026 | Partial Inspection | OSVALDO PARAMO |
| Final | 3/20/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 3/20/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Service/Power Release | 3/20/2026 | Approved | HAMIK HARTOUNIAN |