2438 N HARWOOD ST 90031

Certificate Information: 2438 N HARWOOD ST 90031

Application / Permit
25010-10000-01089
Plan Check / Job No.
B25LA09731
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan DETACHED ADU PER STATE LAW CA GC 66323(a)(2) AND LAMC 2.22 A.33(c)(d) AND (g)
Permit Issued
Issued on 6/26/2025
Issuing Office
Current Status
CofO Issued on 3/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2025 APPLICANT
Assigned to Plan Check Engineer 3/17/2025 LUKE GONZALES
Corrections Issued 3/18/2025 LUKE GONZALES
Applicant returned to address corrections 4/24/2025 KELVIN CHUONG
Plan Check Approved 4/30/2025 LUKE GONZALES
Issued 6/26/2025 APPLICANT
CofO in Progress 3/24/2026 HAMIK HARTOUNIAN
Permit Finaled 3/25/2026 DEROLD HAUFF
CofO Issued 3/25/2026 DEROLD HAUFF
Permit Finaled 3/25/2026 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 3/24/2025 SANDRA SOH
Address approval Cleared 3/25/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/25/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/25/2025 LEE GUILBEAUX
Sewer availability Cleared 3/25/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/25/2025 LEE GUILBEAUX
ZI Cleared 4/14/2025 YINGSHI HUANG

Contact Information

Contractor Smart Eye Construction Corp; Lic. No.: 1077004-B       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/7/2025 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 7/11/2025 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/11/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/12/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 9/12/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 9/26/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/26/2025 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 9/26/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/7/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/20/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 10/20/2025 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 10/20/2025 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 10/21/2025 Conditional Approval GEM DE OCAMPO
Insulation 10/24/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 10/24/2025 Partial Approval DEVON JACKSON
Drywall Nailing 10/29/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/29/2025 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/31/2025 Approved HAMIK HARTOUNIAN
Final 3/17/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 3/17/2026 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 3/17/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 3/17/2026 Approved HAMIK HARTOUNIAN
Special/Order Compliance 3/17/2026 Partial Inspection OSVALDO PARAMO
Final 3/20/2026 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 3/20/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV No Gas HAMIK HARTOUNIAN
Service/Power Release 3/20/2026 Approved HAMIK HARTOUNIAN