5122 E STRATFORD ROAD 90042
Certificate Information: 5122 E STRATFORD ROAD 90042
- Application / Permit
- 25010-10000-01056
- Plan Check / Job No.
- B25LA09313
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW DETACHED 2-STORY ADU PER CITY ORDINANCE WORK DONE PER ENGINEER DESIGN 1 OF 2
- Permit Issued
- Issued on 10/26/2025
- Issuing Office
- Current Status
- Issued on 10/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | KHUONG TRUONG |
| Corrections Issued | 3/30/2025 | KHUONG TRUONG |
| Quality Review Completed | 4/10/2025 | GARO TELMI |
| Applicant returned to address corrections | 9/30/2025 | KHUONG TRUONG |
| Plan Check Approved | 10/20/2025 | KHUONG TRUONG |
| Issued | 10/26/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/14/2025 | MICHAEL TEMPLE |
| Address approval | Cleared | 4/16/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 4/16/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2025 | CINDY QI |
| Sewer availability | Cleared | 4/22/2025 | CINDY QI |
| Construction near power lines | Cleared | 9/25/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Partial Approval | DAVID WILLIAMS |
| Underground Mechanical | 12/11/2025 | Approved | DAVID WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 1/7/2026 | Approved | DAVID WILLIAMS |
| Footing/Foundation/Slab | 1/7/2026 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2026 | Partial Approval | RONNIE MEDINA |
| ELECTRICAL-Rough | 2/25/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 2/25/2026 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 3/12/2026 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2026 | Approved | DAVID WILLIAMS |
| Green Building Rough | 3/12/2026 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 3/12/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 3/31/2026 | Approved | DAVID WILLIAMS |
| Shower Pan | 3/31/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 4/24/2026 | Approved | DAVID WILLIAMS |
| Insulation | 5/11/2026 | Corrections Issued | ALEX COLIN |
| Drywall Nailing | 5/14/2026 | Approved | NICHOLAS LOPEZ |
| Insulation | 5/14/2026 | Approved | NICHOLAS LOPEZ |