1108 E 105TH ST 90002

Certificate Information: 1108 E 105TH ST 90002

Application / Permit
25010-10000-01021
Plan Check / Job No.
B25LA08995
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 10/23/2025
Issuing Office
Current Status
Issued on 10/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/11/2025 APPLICANT
Assigned to Plan Check Engineer 3/14/2025 DANIEL YIP
Corrections Issued 3/14/2025 DANIEL YIP
Applicant returned to address corrections 4/24/2025 DANIEL YIP
Applicant returned to address corrections 4/30/2025 TSE MING HUANG
Applicant returned to address corrections 5/19/2025 DANIEL YIP
Applicant returned to address corrections 6/11/2025 DANIEL YIP
Plan Check Approved 6/26/2025 DANIEL YIP
Issued 10/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/11/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/11/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 4/24/2025 RYAN CASTRO
Sewer availability Cleared 4/30/2025 RYAN CASTRO
Construction within easement Cleared 6/16/2025 WALTER RAMIREZ

Contact Information

Contractor M C General Contractors Inc; Lic. No.: 918838-B       ,
Engineer Mc, Pherson, Matthew Todd; Lic. No.: C50327 13484 APPALACHIAN WY      SAN DIEGO, CA 92129

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/30/2025 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/6/2025 Not Ready for Inspection ANTHONY EGSON
Sewer 11/6/2025 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/12/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 11/12/2025 Corrections Issued ANTHONY EGSON
Sewer 11/12/2025 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/14/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 11/14/2025 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/17/2025 No Access for Inspection ANTHONY EGSON
PLUMBING-Rough 12/8/2025 Approved ARTHUR NEGRETE
Wood Frame 12/8/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Approved ARTHUR NEGRETE
Insulation 12/10/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 2/18/2026 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 2/18/2026 Not Ready for Inspection ANSON MAGLASANG
Green Building Rough 2/18/2026 Not Ready for Inspection ANSON MAGLASANG
HVAC-Rough 2/18/2026 Not Ready for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 2/18/2026 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 2/18/2026 Not Ready for Inspection ANSON MAGLASANG
Verify Sprinkler Sign Off 2/18/2026 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 2/20/2026 Approved ARTHUR NEGRETE
Green Building Rough 2/20/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 2/20/2026 Approved ARTHUR NEGRETE
Rough-Elec/Plmb/HVAC 2/20/2026 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 2/20/2026 Approved ARTHUR NEGRETE
Insulation 3/2/2026 Conditional Approval JOSEPH MCGARRY
Drywall Nailing 3/11/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/11/2026 Approved ARTHUR NEGRETE
Shower Pan 3/11/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 5/13/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 5/13/2026 Approved ARTHUR NEGRETE