15761 W GAULT ST 91406

Certificate Information: 15761 W GAULT ST 91406

Application / Permit
25010-10000-00984
Plan Check / Job No.
B25LA08505
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1 STORY DETACHED ACCESSORY DWELLING UNIT PER WFPP R3 occupancy
Permit Issued
Issued on 4/30/2025
Issuing Office
Current Status
CofO Issued on 1/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2025 APPLICANT
Assigned to Plan Check Engineer 3/10/2025 FERNANDO FLORES
Corrections Issued 3/11/2025 FERNANDO FLORES
Building Plans Picked Up 3/13/2025 APPLICANT
Issued 4/30/2025 APPLICANT
CofO in Progress 1/12/2026 VINCENT HANLEY
Permit Finaled 1/20/2026 RUBEN SALAS
Permit Finaled 1/20/2026 RUBEN SALAS
CofO Issued 1/20/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/24/2025 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 3/24/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/27/2025 BRYAN GODINEZ
Sewer availability Cleared 3/27/2025 BRYAN GODINEZ
Construction near power lines Cleared 4/8/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/28/2025 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 6/9/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Conditional Approval SALVADOR MARTINEZ
ELECTRICAL-Rough 7/18/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 7/18/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 7/18/2025 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 7/18/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/31/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 7/31/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 7/31/2025 Corrections Issued SALVADOR MARTINEZ
MERV13>=Rough 7/31/2025 Not Ready for Inspection SALVADOR MARTINEZ
Verify Sprinkler Sign Off 7/31/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 8/4/2025 Approved VINCENT HANLEY
HVAC-Rough 8/12/2025 Approved GAREN HAYRAPETYAN
Insulation 8/12/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 8/14/2025 Approved SALVADOR MARTINEZ
MERV13>=Rough 8/14/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 8/25/2025 Approved JAVIER RAMOS JR
Shower Pan 8/25/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/29/2025 Partial Approval WAYNE REGESTER
Sewer 10/10/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 11/6/2025 Approved GAREN HAYRAPETYAN
Final 11/6/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 11/6/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 11/6/2025 Approved GAREN HAYRAPETYAN
MERV13>=Final 11/6/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 11/6/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV No Gas GAREN HAYRAPETYAN
Service/Power Release 11/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 11/6/2025 Approved GAREN HAYRAPETYAN
Final 1/9/2026 OK to Issue CofO VINCENT HANLEY
Service/Power Release 1/9/2026 Approved VINCENT HANLEY