1139 N BANNING BLVD 90744

Certificate Information: 1139 N BANNING BLVD 90744

Application / Permit
25010-10000-00946
Plan Check / Job No.
B25LA08049
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY ALL ELECTRIC SINGLE FAMILY DWELLING WITH TRELLIS AND UNCOVERED DECK AT 2ND FLOOR. NFPA-13D FIRE SPRINKLERS TO BE INSTALLED.
Permit Issued
Issued on 3/2/2026
Issuing Office
Current Status
Issued on 3/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/4/2025 APPLICANT
Assigned to Zoning Architect 3/6/2025 KAITA SAITO
Assigned to Plan Check Engineer 3/20/2025 MADISON ODELL
Corrections Issued 3/24/2025 JAD BASMA
Quality Review Completed 3/26/2025 PRANITA SHAH
Applicant returned to address corrections 11/18/2025 MADISON ODELL
Applicant returned to address corrections 12/9/2025 MADISON ODELL
Plan Check Approved 12/17/2025 MADISON O'DELL
Issued 3/2/2026 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 4/1/2025 DALIA MOKAYED
Miscellaneous Cleared 4/15/2025 EDBER MACEDO
Permit Cleared 6/18/2025 XOCHITL ARQUIETA
Address approval Cleared 7/15/2025 XOCHITL ARQUIETA
Abandoned oil well Cleared 8/28/2025 JERRY KAO
Abandoned oil well Cleared 8/28/2025 JERRY KAO
Hydrant and Access approval Cleared 8/28/2025 JERRY KAO
Miscellaneous Cleared 9/29/2025 JERRY KAO
Eng Process Fee Ord 176,300 Cleared 9/30/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 9/30/2025 XOCHITL ARQUIETA
Sewer availability Cleared 9/30/2025 XOCHITL ARQUIETA
Frnt yard landscape/Water mgmt Cleared 10/1/2025 DALIA MOKAYED
Trees in Parkway Cleared 10/10/2025 MIGUEL ORNELAS
Zoning Plan Check Cleared 11/18/2025 KAITA SAITO

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

PLUMBING-Rough 6/22/2026   
Floor/Roof Diaphrgm/Shear Wall 6/23/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/5/2026 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 3/5/2026 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 3/5/2026 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 3/5/2026 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 3/10/2026 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 3/10/2026 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 3/11/2026 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 3/31/2026 Partial Approval JOSEPH MCGARRY
Gas Test 3/31/2026 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 3/31/2026 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 4/20/2026 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 5/13/2026 Partial Approval EUGENE CASSIDY