547 N ERSKINE DR 90272
Certificate Information: 547 N ERSKINE DR 90272
- Application / Permit
- 25010-10000-00944
- Plan Check / Job No.
- B25LA08019
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- *2025 WILDFIRE ELIGIBLE PROJECT* NEW DETACHED 2-CAR GARAGE AT REAR OF LOT. (REBUILD)
- Permit Issued
- Issued on 4/10/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2025 | VIVIAN LAO |
| Assigned to Zoning Architect | 3/5/2025 | VIVIAN LAO |
| Corrections Issued | 3/5/2025 | VIVIAN LAO |
| Quality Review Completed | 3/5/2025 | JOHN FRANCIA |
| Building Plans Picked Up | 3/6/2025 | APPLICANT |
| Applicant returned to address corrections | 3/13/2025 | VIVIAN LAO |
| Plan Check Approved | 3/27/2025 | VIVIAN LAO |
| Issued | 4/10/2025 | APPLICANT |
| CofO in Progress | 4/15/2026 | MEL KHACHATOURIAN |
| Permit Finaled | 4/15/2026 | RICHARD STEINBACH |
| CofO Issued | 4/15/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/15/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2025 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 3/7/2025 | TREVOR QUAN |
| Construction near power lines | Cleared | 3/26/2025 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 3/27/2025 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 3/27/2025 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 3/27/2025 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/29/2025 | Approved | KENNETH NAGLE |
| ELECTRICAL-Rough | 6/6/2025 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 7/3/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 7/3/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Drilled-In Anchors | 8/1/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/18/2025 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/29/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 9/29/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/2/2025 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 1/2/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 1/22/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Service/Power Release | 1/22/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 1/28/2026 | Corrections Issued | MEL KHACHATOURIAN |
| Service/Power Release | 1/28/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 2/11/2026 | Approved | MEL KHACHATOURIAN |
| Service/Power Release | 2/11/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 3/9/2026 | Approved | MICHAEL ALLEN |
| Final | 3/9/2026 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 3/9/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 3/9/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Approved | MICHAEL ALLEN |
| Service/Power Release | 3/9/2026 | Approved | MICHAEL ALLEN |
| Smoke Detectors | 3/9/2026 | Approved | MICHAEL ALLEN |
| Final | 4/10/2026 | OK to Issue CofO | MEL KHACHATOURIAN |