547 N ERSKINE DR 90272

Certificate Information: 547 N ERSKINE DR 90272

Application / Permit
25010-10000-00943
Plan Check / Job No.
B25LA08019
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING W/ PORTE COCHERE (REPLACEMENT) NFPA 13D SOLAR INSTALLATION REQUIRED TO MEET #KW PER TITLE 24 PRIOR TO COFO.
Permit Issued
Issued on 4/10/2025
Issuing Office
Metro
Current Status
CofO Issued on 4/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2025 APPLICANT
Assigned to Plan Check Engineer 3/5/2025 VIVIAN LAO
Assigned to Zoning Architect 3/5/2025 VIVIAN LAO
Corrections Issued 3/5/2025 VIVIAN LAO
Quality Review Completed 3/5/2025 JOHN FRANCIA
Building Plans Picked Up 3/6/2025 APPLICANT
Applicant returned to address corrections 3/13/2025 VIVIAN LAO
Plan Check Approved 3/27/2025 VIVIAN LAO
Issued 4/10/2025 APPLICANT
CofO in Progress 4/15/2026 MEL KHACHATOURIAN
Permit Finaled 4/15/2026 RICHARD STEINBACH
CofO Issued 4/15/2026 RICHARD STEINBACH
Permit Finaled 4/15/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/7/2025 TREVOR QUAN
Roof/Waste drainage to street Cleared 3/7/2025 TREVOR QUAN
Sewer availability Cleared 3/7/2025 TREVOR QUAN
GPI Written Notices Cleared 3/27/2025 VIVIAN LAO
Grading Pre-Inspection Cleared 3/27/2025 VIVIAN LAO
Hydrant and Access approval Cleared 3/27/2025 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/18/2025 Partial Inspection BOBBY KEY
Special/Order Compliance 5/13/2025 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 5/29/2025 Partial Approval KENNETH NAGLE
ELECTRICAL-Rough 6/6/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 6/9/2025 Approved KENNETH NAGLE
BUILDING-Rough-Frame 6/18/2025 Partial Approval MEL KHACHATOURIAN
Green Building Rough 6/18/2025 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 6/18/2025 Partial Approval MEL KHACHATOURIAN
Verify Sprinkler Sign Off 6/18/2025 Not Ready for Inspection MEL KHACHATOURIAN
Insulation 6/20/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval STEPHANIE SWANSON
Green Building Rough 7/2/2025 Not Ready for Inspection STEPHANIE SWANSON
Verify Sprinkler Sign Off 7/2/2025 Not Ready for Inspection STEPHANIE SWANSON
Deputy Wood Construction 8/1/2025 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/27/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 9/17/2025 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 9/17/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 9/17/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 9/17/2025 Conditional Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 9/18/2025 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 9/29/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 9/29/2025 Corrections Issued STEPHANIE SWANSON
Green Building Rough 9/29/2025 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 9/29/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 10/2/2025 Approved STEPHANIE SWANSON
Insulation 10/2/2025 Partial Approval STEPHANIE SWANSON
Insulation 10/10/2025 Approved MEL KHACHATOURIAN
Drywall Nailing 10/17/2025 Approved MEL KHACHATOURIAN
Sewer 10/28/2025 Approved MEL KHACHATOURIAN
Underground Mechanical 10/28/2025 Partial Approval MEL KHACHATOURIAN
Service/Power Release 1/2/2026 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Final 1/22/2026 Not Ready for Inspection MEL KHACHATOURIAN
Service/Power Release 1/22/2026 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 1/28/2026 Not Ready for Inspection MEL KHACHATOURIAN
Service/Power Release 1/28/2026 Corrections Issued MEL KHACHATOURIAN
Gas Test 2/5/2026 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 2/11/2026 Approved MEL KHACHATOURIAN
Service/Power Release 2/11/2026 Conditional Approval MEL KHACHATOURIAN
HVAC-Final 2/18/2026 Conditional Approval MEL KHACHATOURIAN
PLUMBING-Final 2/19/2026 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 2/19/2026 SGSOV Approved STEPHANIE SWANSON
Final 3/9/2026 Corrections Issued MICHAEL ALLEN
Green Building Final 3/9/2026 Approved MICHAEL ALLEN
Service/Power Release 3/9/2026 Approved MICHAEL ALLEN
Smoke Detectors 3/9/2026 Approved MICHAEL ALLEN
Final 4/10/2026 OK to Issue CofO MEL KHACHATOURIAN