3435 W HOLLYDALE DR 90039

Certificate Information: 3435 W HOLLYDALE DR 90039

Application / Permit
25010-10000-00926
Plan Check / Job No.
B25LA07906
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] NEW 2-STORY ADU PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 10/28/2025
Issuing Office
Current Status
Issued on 10/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/3/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 MAHNAZ NOURHASHEMI
Corrections Issued 4/2/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 4/18/2025 HERNAN ARREOLA
Applicant returned to address corrections 7/6/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 9/4/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 9/10/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 9/18/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 10/8/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 10/15/2025 MAHNAZ NOURHASHEMI
Issued 10/28/2025 APPLICANT

Permit Application Clearance Information

ZI Cleared 4/23/2025 DANIEL CORONADO
Roof/Waste drainage to street Cleared 4/27/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 4/28/2025 TAL SHEMEN
Address approval Cleared 5/6/2025 TAL SHEMEN
Sewer availability Cleared 5/6/2025 TAL SHEMEN
Construction near power lines Cleared 10/8/2025 RIDWAN HARDY
Construction within easement Cleared 10/8/2025 RIDWAN HARDY

Contact Information

Contractor Ground Up Builders And Design Inc; Lic. No.: 911849-B       ,
Contractor Ground Up Builders; Lic. No.: 911849-B       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Almalla,, Dean; Lic. No.: NA58024       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2025 Partial Inspection NICHOLAS LOPEZ
PLUMBING-Rough 11/25/2025 Partial Approval NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 12/3/2025 Approved NICHOLAS LOPEZ
Footing/Foundation/Slab 12/3/2025 Approved NICHOLAS LOPEZ
Wood Frame 12/10/2025 No Access for Inspection NICHOLAS LOPEZ
Underground Mechanical 12/12/2025 Partial Approval NICHOLAS LOPEZ
Wood Frame 12/12/2025 Partial Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/23/2026 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 2/10/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 2/10/2026 Approved NICHOLAS LOPEZ
Green Building Rough 2/10/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 2/10/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 2/10/2026 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 2/10/2026 Approved NICHOLAS LOPEZ
Verify Sprinkler Sign Off 2/10/2026 Approved NICHOLAS LOPEZ
Insulation 2/20/2026 Conditional Approval NICHOLAS LOPEZ
Drywall Nailing 2/27/2026 Partial Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 2/27/2026 Approved NICHOLAS LOPEZ
Pre-Inspection 2/27/2026 Partial Inspection NICHOLAS LOPEZ
Shower Pan 2/27/2026 Approved NICHOLAS LOPEZ
Drywall Nailing 3/2/2026 Approved NICHOLAS LOPEZ
Shower Pan 3/2/2026 Approved NICHOLAS LOPEZ
Sewer 5/22/2026 Approved NICHOLAS LOPEZ