1658 N RAVENNA AVE 90744

Certificate Information: 1658 N RAVENNA AVE 90744

Application / Permit
25010-10000-00885
Plan Check / Job No.
B25LA07534
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY DETACHED ADU PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 4/30/2025
Issuing Office
Metro
Current Status
CofO Issued on 1/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2025 APPLICANT
Assigned to Plan Check Engineer 3/5/2025 LUKE GONZALES
Corrections Issued 3/6/2025 LUKE GONZALES
Building Plans Picked Up 3/12/2025 APPLICANT
Applicant returned to address corrections 4/18/2025 EDWIN MARTINEZ
Plan Check Approved 4/30/2025 DANIEL SMILEY
Issued 4/30/2025 APPLICANT
CofO in Progress 1/5/2026 JOSEPH MCGARRY
Permit Finaled 1/5/2026 ANSON MAGLASANG
CofO Issued 1/5/2026 ANSON MAGLASANG
Permit Finaled 1/5/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/18/2025 FRANK SALAZAR
Eng Process Fee Ord 176,300 Cleared 3/18/2025 FRANK SALAZAR
Roof/Waste drainage to street Cleared 3/18/2025 FRANK SALAZAR
Sewer availability Cleared 3/18/2025 FRANK SALAZAR
ZA Case Cleared 3/20/2025 MATHEW QUAN
ZI Cleared 3/20/2025 MATHEW QUAN

Contact Information

Contractor Hilltop Design-Build Inc; Lic. No.: 969696-B 1441 W 7TH STREET 2ND FLOOR      SAN PEDRO, CA 90732
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/21/2025 Approved EUGENE CASSIDY
METHANE-Barrier 5/21/2025 Approved EUGENE CASSIDY
METHANE-Subgrade 5/21/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 5/30/2025 Partial Approval JOSEPH MCGARRY
Sewer 5/30/2025 Approved JOSEPH MCGARRY
Wood Frame 5/30/2025 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 6/2/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 7/21/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 7/21/2025 Approved EUGENE CASSIDY
METHANE-Rough 7/21/2025 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 7/21/2025 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 7/21/2025 Approved EUGENE CASSIDY
Insulation 8/15/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/15/2025 Partial Approval EUGENE CASSIDY
Drywall Nailing 8/25/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/25/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 12/10/2025 Approved EUGENE CASSIDY
Final 12/10/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 12/10/2025 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 12/10/2025 Not Required EUGENE CASSIDY
Smoke Detectors 12/10/2025 Approved EUGENE CASSIDY
Final 12/19/2025 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 12/19/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved EUGENE CASSIDY
Final 12/31/2025 OK to Issue CofO JOSEPH MCGARRY