18020 W WELBY WAY 91335

Certificate Information: 18020 W WELBY WAY 91335

Application / Permit
25010-10000-00828
Plan Check / Job No.
B25LA07093
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. NEW A.D.U. DETACHED
Permit Issued
Issued on 5/6/2025
Issuing Office
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2025 APPLICANT
Assigned to Plan Check Engineer 2/28/2025 FERNANDO FLORES
Corrections Issued 3/3/2025 FERNANDO FLORES
Applicant returned to address corrections 3/13/2025 FERNANDO FLORES
Plan Check Approved 4/17/2025 FERNANDO FLORES
Issued 5/6/2025 APPLICANT
CofO in Progress 12/18/2025 ARUTYUN MADATYAN
Permit Finaled 1/2/2026 JOHN JANSON
CofO Issued 1/2/2026 JOHN JANSON
Permit Finaled 1/2/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/3/2025 PAMELA TENEZA
Roof/Waste drainage to street Cleared 3/4/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/5/2025 BIAINA HARITUNIAN
ZI Cleared 3/5/2025 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 3/6/2025 PAMELA TENEZA
Construction within easement Cleared 4/16/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/22/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 5/22/2025 Partial Approval ARUTYUN MADATYAN
Sewer 5/22/2025 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 5/30/2025 Approved ARUTYUN MADATYAN
Underground Mechanical 5/30/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 7/16/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 7/16/2025 Approved ARUTYUN MADATYAN
Green Building Rough 7/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 7/16/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 7/16/2025 Approved ARUTYUN MADATYAN
Wood Frame 7/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/21/2025 Partial Inspection ROBERT GOLD
Green Building Final 7/21/2025 Not Ready for Inspection ROBERT GOLD
Green Building Rough 7/21/2025 Approved ROBERT GOLD
HVAC-Final 7/21/2025 Not Ready for Inspection ROBERT GOLD
Interior/Exterior Lathing 7/21/2025 Partial Approval ROBERT GOLD
PLUMBING-Final 7/21/2025 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 7/21/2025 SGSOV Not Ready ROBERT GOLD
Service/Power Release 7/21/2025 Not Ready for Inspection ROBERT GOLD
Smoke Detectors 7/21/2025 Not Ready for Inspection ROBERT GOLD
BUILDING-Rough-Frame 7/25/2025 Approved ROBERT GOLD
Insulation 7/25/2025 Corrections Issued ROBERT GOLD
Insulation 7/30/2025 Approved GEVORK IPCHYAN
Drywall Nailing 8/4/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 8/12/2025 Approved AMY COLIN
Shower Pan 8/12/2025 Approved AMY COLIN
ELECTRICAL-Rough 8/14/2025 Partial Inspection ARUTYUN MADATYAN
Green Building Final 10/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 10/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 10/16/2025 Corrections Issued ARUTYUN MADATYAN
Final 10/20/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 10/20/2025 No Access for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/20/2025 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 10/20/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 10/20/2025 Approved ARUTYUN MADATYAN
Service/Power Release 10/22/2025 No Access for Inspection ARUTYUN MADATYAN
Final 10/29/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 10/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 10/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 12/18/2025 Approved ARUTYUN MADATYAN
Final 12/18/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 12/18/2025 Approved ARUTYUN MADATYAN
HVAC-Final 12/18/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 12/18/2025 Approved ARUTYUN MADATYAN
Service/Power Release 12/18/2025 Approved ARUTYUN MADATYAN