4262 S ALLA ROAD 90066
Certificate Information: 4262 S ALLA ROAD 90066
- Application / Permit
- 25010-10000-00815
- Plan Check / Job No.
- B24LA38405
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: NEW 2-STORY DETACHED STATE ADU PER GC 66323(a)(2) WITH ATTACHED 2-CAR GARAGE FIre Sprinkler throughout
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Current Status
- Issued on 8/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | KHEDER ALRAZAA |
| Corrections Issued | 2/21/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 2/26/2025 | GARO TELMI |
| Applicant returned to address corrections | 3/21/2025 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 5/7/2025 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 7/24/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 8/29/2025 | KHEDER ALRAZAA |
| Issued | 8/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2025 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2025 | LIAM ODONOVAN |
| Sewer availability | Cleared | 6/16/2025 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 7/2/2025 | CARLOS AGUILERA |
| Specific Plan | Cleared | 7/30/2025 | HAMID GHAEMMAGHAMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: NA83859 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/16/2025 | Partial Approval | WILBER ROSALES |
| Underground Mechanical | 10/16/2025 | Approved | WILBER ROSALES |
| Footing/Foundation/Slab | 10/21/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 10/21/2025 | Not Ready for Inspection | WILBER ROSALES |
| Verify Sprinkler Sign Off | 10/21/2025 | Not Ready for Inspection | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Partial Approval | WILBER ROSALES |
| Green Building Rough | 10/31/2025 | Not Ready for Inspection | WILBER ROSALES |
| Verify Sprinkler Sign Off | 10/31/2025 | Not Ready for Inspection | WILBER ROSALES |
| Wood Frame | 10/31/2025 | Not Ready for Inspection | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 12/4/2025 | Corrections Issued | WILBER ROSALES |
| ELECTRICAL-Rough | 12/4/2025 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Rough | 12/4/2025 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Rough | 12/4/2025 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Rough | 12/4/2025 | Not Ready for Inspection | WILBER ROSALES |
| Verify Sprinkler Sign Off | 12/4/2025 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Rough | 1/13/2026 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 1/13/2026 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 1/13/2026 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/2/2026 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 2/2/2026 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 2/2/2026 | Partial Approval | ANTHONY EGSON |
| Sewer | 2/2/2026 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/11/2026 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | Approved | MICHAEL ALLEN |
| Green Building Rough | 2/11/2026 | Approved | MICHAEL ALLEN |
| Insulation | 2/11/2026 | Conditional Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 2/11/2026 | Partial Approval | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 2/11/2026 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 2/18/2026 | Approved | DAKOTA LOW |
| Insulation | 2/18/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 2/24/2026 | Partial Approval | DAKOTA LOW |
| Shower Pan | 2/27/2026 | Approved | DAKOTA LOW |